Summary
A 30-50 MW renewable energy facility near ECG's Dawhenya substation in Tema, phased in over its first months of operation, supplying ECG under a 15-year energy-only PPA signed 27 November 2007 (reviewed/renewed every 5 years). The energy charge is 7.0 US cents/kWh or the PURC Bulk Generation Tariff if higher, capped at 10 US cents/kWh for the first 10 years, with under-consumption/under-supply penalty adjustments and a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2007-11-27
- Financial close
- —
- Commercial operation
- —
- Contract end
- 2022-11-27
- Contract duration
- 15 years
- Contract status
- Active
- Tariff structure
- Energy-only
- Capacity charge
- —
- Energy charge
- USD 7.0000/kWh
- Key risk features
- Take-or-pay
- Indexation formula
- Flat USD rate of 7.0 US cents/kWh (or the PURC Bulk Generation Tariff if higher), capped at 10 US cents/kWh, for the first 10 years; renegotiated with PURC and ECG thereafter, with no stated floor. Paid in USD or its cedi equivalent at the prevailing Interbank rate; no hedging mechanism.