GH-PPA-12

TC's Energy 1,000 MW Sea Wave and Tidal Project, Ada

TC's Energy Limited · Tidal / Wave · 1000.00 MW · Ada, Greater Accra Region, Ghana

Summary

A sea wave and tidal energy project in Ada, built in six stages to a cumulative ~1,000 MW, supplying ECG under a 20-year energy-only PPA signed 14 July 2014. A flat tariff of 10.00 US cents/kWh applies for the first 10 years, renegotiated within a PURC range thereafter, with a take-or-pay obligation and an annual minimum-offtake compensation mechanism once fully built out.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2014-07-14
Financial close
Not stated
Commercial operation
Within 3 years of PPA signing (i.e. by July 2017) (cl. 15.1.17); Schedule 7 schedules the final Stage 6 Unit (the full 1,000 MW) for January 2017 Source: cl. 15.1.17; Sch. 7 (p. 21; 41)
Contract end
Not stated
Contract duration
20 years
Contract status
Active
Project status
Not recorded
Tariff structure
Energy-only
Capacity charge
Not stated
Energy charge
USD 0.1/kWh
Key risk features
Take-or-pay Currency indexation
Indexation formula
Fixed USD rate for years 1-10, paid in Ghana cedis via a quarterly Exchange Rate Hedge Agreement; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 10 years. Once Stage 6 is operating, an annual Compensation/Discount mechanism reconciles actual annual offtake against a 7,817.4-8,327.3 GWh band.
Project overview
Commercial operation date (COD)
Within 3 years of PPA signing (i.e. by July 2017) (cl. 15.1.17); Schedule 7 schedules the final Stage 6 Unit (the full 1,000 MW) for January 2017 Source: cl. 15.1.17; Sch. 7 (p. 21; 41)
Contract term (years)
20 Source: cl. 2.1 (p. 11)
Contracting parties
Transmission service provider
Electricity Transmission Utility (ETU); GridCo is separately defined as the current operator of the NITS Source: 'ETU', 'GridCo' definitions; cl. 4.2 (p. 7; 12)
Government support entity
Not addressed in the PPA; may be addressed in related documents.
Project sponsors / shareholders
Not in contract
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Energy-Only PPA Source: cl. 9.1; Sch. 1 (p. 15; 32)
Contracted capacity (MW)
Approximately 1,000 (cumulative, reached at Stage 6) Source: 'Contracted Capacity' definition (p. 6)
Tariff currency
US Dollars, invoiced monthly and paid in Ghana cedis converted via a quarterly Exchange Rate Hedge Agreement Source: cl. 9.6-9.7 (p. 15-16)
Tariff structure summary
Single flat energy rate of US 10.00 cents/kWh (Total Energy Charge = Tariff x Energy Generated) for the first 10 years of operation; price then renegotiated within a PURC range for the remaining 10 years, with a floor at the initial rate. Once Stage 6 is operating, an annual Compensation/Discount mechanism (cl. 9.14-9.15) reconciles actual annual offtake against a contracted band of 7,817.4 to 8,327.3 GWh. Source: Sch. 1; cl. 9.14-9.15 (p. 32; 16-17)
Energy charge
US 10.00 cents/kWh on energy generated/delivered at the Delivery Point (Total Energy Charge = Tariff x Energy generated in kWh) Source: Sch. 1 (p. 32)
Tariff escalation mechanism
No escalation for 10 years. From year 11, price renegotiated within the PURC range; cannot fall below the initial rate, applying for the remaining 10 years of the 20-year term. Source: Sch. 1 para 2 (p. 32)
Indexation: inflation
No Source: Sch. 1 (p. 32)
Indexation: foreign exchange
Yes Source: cl. 9.6-9.7 (p. 15-16)
Indexation: fuel price
No
Indexation: none / fixed tariff
Yes Source: Sch. 1 (p. 32)
Indexation: other
No
Summary of indexation methodology
Fixed USD rate for years 1-10, paid in Ghana cedis via a quarterly Exchange Rate Hedge Agreement communicated to and accepted by PURC; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 10 years. Once Stage 6 is operating, cl. 9.14-9.15 reconcile actual annual offtake against a 7,817.4-8,327.3 GWh band via an Annual Compensation or Discount. Source: Sch. 1; cl. 9.6-9.7; 9.14-9.15 (p. 32; 15-17)
Government and consumer exposure
Take-or-pay obligation
Yes Source: cl. 4.3 (p. 12)
Take-or-pay details
Buyer must buy all energy produced from the Commercial Operation Date of the first unit and pay the tariff for energy produced under the Seller's Energy Production Program but not taken. Once Stage 6 is operating, cl. 9.14 additionally requires the Buyer to pay an Annual Compensation if its actual annual offtake falls below the contracted Annual Energy of 7,817.4 GWh for reasons attributable to the Buyer. Source: cl. 4.3; 9.14 (p. 12; 16-17)
Minimum offtake requirement
Yes Source: cl. 4.3; 9.14 (p. 12; 16-17)
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 9.6-9.7 (p. 15-16)
Foreign exchange protection details
Tariff invoiced monthly in USD but paid in Ghana cedis using an exchange rate the Seller fixes each quarter under an Exchange Rate Hedge Agreement with a Ghanaian commercial bank, which must be communicated to and accepted by PURC before use; the PPA does not state who bears the hedge's cost. Source: cl. 9.6-9.7 (p. 15-16)
Other government commitments
None found beyond regulatory filing conditions precedent: the Seller must obtain all required regulatory consents, a Connection Agreement, an approved feed-in tariff from PURC, and an Energy Commission construction permit and operating licence before the Effective Date. No Ministry no-objection, sovereign guarantee, or comparable government undertaking is stated as a Buyer or government obligation. Separately, the Buyer is entitled to 50% of any proceeds from the sale of Renewable Energy Certificates generated by the project (cl. 30.2). Source: cl. 3.1-3.2; 30.2 (p. 11-12; 30)
Fiscal incentives and non-tariff government support
None found in the PPA: no tax holiday, duty/VAT exemption or stabilization clause.
Risk allocation
Fuel supply risk borne by
Not applicable
Resource availability risk borne by
Seller Source: cl. 15.1.18; 19.1.1 (p. 21; 25)
Foreign exchange risk borne by
Shared Source: cl. 9.6-9.7 (p. 15-16)
Transmission and grid availability risk borne by
Offtaker Source: cl. 4.2; 15.1.16 (p. 12; 21)
Summary of key risk allocation provisions
Fuel risk: not applicable (sea wave/tidal). Resource-availability risk sits with the Seller, measured against its own Annual Energy Production Program. FX: the tariff is invoiced in USD and paid in cedis at the rate fixed under the Seller's quarterly Exchange Rate Hedge Agreement, so FX risk is shared: the Buyer bears cedi depreciation, and any spread between the hedge rate and the Seller's actual conversion cost stays with the Seller; the PPA does not say who pays for the hedge. Change in Law is defined but never used operatively (not addressed). Transmission/grid risk sits with the Buyer, which must arrange transmission with the ETU and for which the ETU bears sole responsibility for the connecting line. The Buyer carries take-or-pay/must-run exposure (cl. 4.3) plus, once Stage 6 is complete, an Annual Compensation if it under-takes contracted energy (cl. 9.14); the Seller carries liquidated damages of USD 200,000/day, secured by a USD 20,000,000 Performance Bond, if commissioning is late (cl. 8.4-8.5). Source: cl. 4.2-4.3; 8.4-8.5; 9.6-9.7; 9.14; 15.1.16; 15.1.18; 19.1.1; 'Change in Law' definition
Performance obligations
Availability requirement
No stated availability percentage. Seller is in default if energy supplied over any 30 continuous days is below 50% of the amount in the Annual Energy Production Program in Schedule 7. Source: cl. 19.1.1 (p. 25)
Summary of performance obligations
If the Commercial Operation Date (tied to completion of the Stage 6 Unit) is delayed beyond the Scheduled Commercial Operation Date, the Seller pays liquidated damages of USD 200,000 per day, which the Buyer may draw from the Seller's USD 20,000,000 Performance Bond (posted from the Effective Date and released about 3 months after the Commissioning Certificate). Separately, the Seller warrants sufficient installed capacity to meet its own Annual Energy Production Program (cl. 7.2); default trigger for undersupply is delivery below 50% of the Program over 30 continuous days (cl. 19.1.1). From the second year after the Stage 6 Commercial Operation Date, if annual energy delivered falls below 7,817.4 GWh for reasons attributable to the Seller, the Seller pays the Buyer the cost difference of replacement energy bought at the system marginal or spot price (cl. 9.14(a)). Source: cl. 7.2; 8.4-8.5; 9.14; 19.1.1 (p. 14; 14-15; 16; 25)
Curtailment compensation
Applicable Source: cl. 4.3; 15.2.8 (p. 12; 22)
Summary of curtailment arrangements
Buyer pays the tariff for energy produced per the Seller's Energy Production Program but not taken (cl. 4.3), and, once Stage 6 is complete, pays an Annual Compensation if it under-takes the contracted energy band for reasons attributable to the Buyer (cl. 9.14). The Buyer may curtail or interrupt in emergencies at its sole discretion (cl. 15.2.8); the PPA does not say whether emergency curtailment is separately compensated. Source: cl. 4.3; 9.14; 15.2.8 (p. 12; 16-17; 22)
Force majeure, default and termination
Force majeure provisions
Force Majeure covers any event beyond the Affected Party's reasonable control that it could not prevent despite diligence, is not its own breach, and is without its fault, including war/armed conflict/insurrection/terrorism, acts of God, and epidemics (cl. 17.1). The Affected Party must report within 7 days and continue mitigation/progress reports (cl. 17.2-17.3). The Buyer must keep paying the Seller for energy delivered during a Seller-side Force Majeure event, and the Buyer cannot claim Force Majeure for its own payment obligations (cl. 17.5). No Force Majeure-linked termination right or compensation payment is stated in Clause 17 itself; termination for Force Majeure is only available by mutual agreement (cl. 20.2.2(c)). Source: cl. 17.1-17.5; 20.2.2(c) (p. 23-24; 26)
Termination compensation: seller default
Not stated Source: cl. 20.1.1; 19.3.2 (p. 26)
Termination compensation: buyer default
Not stated Source: cl. 20.1.2; 19.3.2 (p. 26)
Termination compensation: political force majeure
Not stated Source: cl. 17; 20.2.2(c) (p. 23-24; 26)
Summary of termination compensation framework
The only termination payment stated is on a conditions-precedent termination: if the Buyer terminates for unsatisfied conditions precedent while the Seller is meeting the Schedule 6 milestones, it must first pay all verifiable costs the Seller has incurred (cl. 3.3). Otherwise there is no termination payment formula in the PPA. Any defaulting Party's liabilities accrued before termination survive, and the Buyer remains liable for Electrical Energy already supplied (cl. 20.1.3). Either Party may claim compensation for losses from the other's default, including lost revenues and expected profit (cl. 19.3.2). On Buyer default, the Seller may remove its equipment at the Buyer's expense and draw on the Buyer's US$5,000,000 payment guarantee (cl. 9.9; 20.1.2). Separately, late commissioning triggers liquidated damages of USD 200,000/day, drawable from the Seller's USD 20,000,000 Performance Bond (cl. 8.4-8.5), which is a distinct, commissioning-specific instrument, not a general termination payment. The facility remains with the Seller after expiry or termination (cl. 20.2.3). Source: cl. 3.3; 8.4-8.5; 9.9; 19.3.2; 20.1.2-20.1.3; 20.2.3 (p. 12; 14-15; 16; 26-27)
Dispute resolution
Governing law
Laws of the Republic of Ghana Source: cl. 29 (p. 29)
Dispute resolution: negotiation / mediation
Yes Source: cl. 22.1 (p. 27)
Dispute resolution: expert determination
No
Dispute resolution: arbitration
Yes Source: cl. 22.2 (p. 27)
Dispute resolution: court proceedings
No
Dispute resolution: other
No
Arbitration seat
London, England Source: cl. 22.2.3 (p. 27)
Applicable arbitration rules
London Court of International Arbitration (LCIA); 3 arbitrators; English language Source: cl. 22.2.1-22.2.3 (p. 27)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 24.1 (p. 27-28)