GH-PPA-DRAFT-11
Savanna Solar 400 MW Solar PV Project, Kusawgu
Savanna Solar Limited · Solar PV · 400.00 MW · Kusawgu, Northern Region, Ghana
GH-PPA-DRAFT-11
Savanna Solar 400 MW Solar PV Project, Kusawgu
Savanna Solar Limited · Solar PV · 400.00 MW · Kusawgu, Northern Region, Ghana
Summary
A 400 MW solar PV plant in Kusawgu, Northern Region, supplying ECG under a 25-year energy-only PPA signed 11 June 2013 (extendable by 5 years). A flat PURC feed-in tariff of 22.6372 US cents/kWh applies for the first 10 years, renegotiated within a PURC range thereafter, with a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2013-06-11
- Financial close
- —
- Commercial operation
- —
- Contract end
- —
- Contract duration
- 25 years
- Contract status
- Active
- Tariff structure
- Energy-only
- Capacity charge
- —
- Energy charge
- USD 22.6372/kWh
- Key risk features
- Take-or-pay
- Indexation formula
- Fixed USD rate for years 1-10; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 15 years.