GH-PPA-11
Savanna Solar 400 MW Solar PV Project, Kusawgu
Savanna Solar Limited · Solar PV · 400.00 MW · Kusawgu, Northern Region, Ghana
GH-PPA-11
Savanna Solar 400 MW Solar PV Project, Kusawgu
Savanna Solar Limited · Solar PV · 400.00 MW · Kusawgu, Northern Region, Ghana
Summary
A 400 MW solar PV plant in Kusawgu, Northern Region, supplying ECG under a 25-year energy-only PPA signed 11 June 2013 (extendable by 5 years). A flat PURC feed-in tariff of 22.6372 US cents/kWh applies for the first 10 years, renegotiated within a PURC range thereafter, with a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2013-06-11
- Financial close
- Not stated
- Commercial operation
- Within 3 years of PPA signing (i.e. by June 2016) Source: cl. 15.1.17 (p. 15)
- Contract end
- 25 years from the Effective Date (extendable by 5 years by mutual consent) Source: cl. 2.1; 2.2 (p. 8)
- Contract duration
- 25 years
- Contract status
- Active
- Project status
- Not recorded
- Tariff structure
- Energy-only
- Capacity charge
- None (no capacity payment) Source: Sch. 1 (p. 26)
- Energy charge
- USD 0.226372/kWh
- Key risk features
- Take-or-pay
- Indexation formula
- Fixed USD rate for years 1-10; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 15 years.
Project overview
- Expected annual generation
- Not in contract Source: cl. 6.1-6.2 (p. 9)
- Commercial operation date (COD)
- Within 3 years of PPA signing (i.e. by June 2016) Source: cl. 15.1.17 (p. 15)
- PPA expiry
- 25 years from the Effective Date (extendable by 5 years by mutual consent) Source: cl. 2.1; 2.2 (p. 8)
- Contract term (years)
- 25 (extendable by 5 years by mutual consent; year-to-year thereafter) Source: cl. 2.1; 2.2; 20.2.1 (p. 8; 20)
Contracting parties
- Transmission service provider
- Ghana Grid Company (GRIDCo) Source: cl. 4.2; 15.1.16 (p. 8; 15)
- Government support entity
- Not addressed in the PPA; may be addressed in related documents. Recital: the seller will need the Buyer's and the Ministry's assistance to obtain political risk insurance. Source: Recitals (p. 2)
- Project sponsors / shareholders
- Not stated in the PPA
- Ultimate beneficial owner(s)
- Not in contract
Commercial terms
- Contract type
- Energy-Only PPA Source: cl. 8.1; Sch. 1 (p. 10; 26)
- Contracted capacity (MW)
- 400 Source: 'Connected Capacity' definition (p. 3)
- Tariff currency
- US Dollars (invoiced and payable in USD) Source: cl. 8.6 (p. 11)
- Tariff structure summary
- Single flat energy rate of US 22.6372 cents/kWh for the first 10 years of operation; price then renegotiated within a PURC range for the remaining 15 years, with a floor at the initial rate. The rate is labelled a PURC Feed-In-Tariff, and a FIT framework is a condition precedent to effectiveness. Source: Sch. 1; cl. 3.1(e); 'Feed-In-Tariff' definition (p. 26; 8; 4)
- Capacity charge
- None (no capacity payment) Source: Sch. 1 (p. 26)
- Energy charge
- US 22.6372 cents/kWh on metered energy delivered (Ei = supply meter reading less compensator consumption) Source: Sch. 1; Sch. 3 para 3 (p. 26; 30)
- Tariff escalation mechanism
- No escalation for 10 years. From year 11, price renegotiated within PURC range; cannot fall below the initial rate. Source: Sch. 1 para 2 (p. 26)
- Indexation: inflation
- No Source: Sch. 1 (p. 26)
- Indexation: foreign exchange
- No Source: cl. 8.6 (p. 11)
- Indexation: fuel price
- No
- Indexation: none / fixed tariff
- Yes Source: Sch. 1 (p. 26)
- Indexation: other
- No
- Summary of indexation methodology
- Fixed USD rate for years 1-10; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 15 years. Source: Sch. 1 (p. 26)
Government and consumer exposure
- Take-or-pay obligation
- Yes Source: cl. 4.3 (p. 8)
- Take-or-pay details
- ECG must buy all energy produced from COD and pay the tariff for energy produced under the Seller's production program but not taken. Source: cl. 4.3 (p. 8)
- Minimum offtake requirement
- Yes Source: cl. 4.3 (p. 8)
- Minimum offtake details
- 100% of energy produced (must-run facility); undelivered-but-available energy paid as deemed energy. Source: cl. 4.3; 'MUST RUN Facility' definition (p. 8; 5)
- Government guarantee
- No
- Letter of support
- No
- Foreign exchange protection mechanism
- Yes Source: cl. 8.6 (p. 11)
- Foreign exchange protection details
- Tariff invoiced and payable in US dollars, so the seller bears no cedi depreciation risk. Source: cl. 8.6 (p. 11)
- Other government commitments
- Offtaker (not Government): ECG must post a USD 15 million standby letter of credit or bank guarantee from an international bank, stepping down to about 2 months of payments after construction. Recital: seller will need Buyer and Ministry assistance to obtain World Bank political risk insurance. Source: cl. 8.8; Recitals (p. 11; 2)
- Fiscal incentives and non-tariff government support
- VAT not charged on energy invoiced. ECG builds the connection point and transmission lines to the substation at its own cost; GRIDCo solely responsible for the line to the NITS. ECG receives 50% of any REC/SREC sale proceeds. No tax holiday or stabilization clause found. Source: cl. 8.9; 5.2; 15.1.16; 30.2 (p. 11; 9; 15; 23)
Risk allocation
- Fuel supply risk borne by
- Not applicable
- Resource availability risk borne by
- Seller Source: cl. 7.2; 19.1.1 (p. 10; 19)
- Foreign exchange risk borne by
- Offtaker Source: cl. 8.6 (p. 11)
- Transmission and grid availability risk borne by
- Offtaker Source: cl. 4.2; 4.3; 5.2; 15.1.16 (p. 8; 9; 15)
- Summary of key risk allocation provisions
- ECG carries offtake, FX and grid risk: it must buy all output (and pay for energy not taken), pays in USD, and builds the connection and lines. Seller carries resource and performance risk. Change in law is defined but not allocated. Fuel risk not applicable (solar). Source: cl. 4.3; 5.2; 8.6; 15.1.16; 19.1.1 (p. 8-19)
Performance obligations
- Availability requirement
- No availability percentage. Seller is in default if energy supplied over any 30 continuous days, or over the year, is below 50% of its Annual Energy Production Program. Source: cl. 19.1.1 (p. 19)
- Performance guarantee
- No Source: cl. 7.2 (p. 10)
- Summary of performance obligations
- Seller warrants sufficient capacity for its own production program, reports monthly/annually, delivers 3-phase power at 161 kV within grid code limits, and maintains 0.9 power factor. Default threshold is 50% of programmed output. Source: cl. 6; 7; 15.1; 19.1.1 (p. 9-15; 19)
- Curtailment compensation
- Applicable Source: cl. 4.3; 15.2.8 (p. 8; 16)
Force majeure, default and termination
- Force majeure provisions
- Broad definition incl. war, riots, natural events, fuel shortage and government action or inaction (except payment default). Obligations suspended while FM continues; no payment relief or termination payment specified. Lack of funds excluded. Source: cl. 17 (p. 17-18)
- Termination compensation: seller default
- Not stated Source: cl. 19.3.2 (p. 19)
- Termination compensation: buyer default
- Not stated Source: cl. 19.3.2; 20.1.3 (p. 19-20)
- Termination compensation: political force majeure
- Not stated
- Summary of termination compensation framework
- No termination payment formula in the PPA. Either party may claim losses from the other's default, including lost profit (cl. 19.3.2). Termination does not relieve accrued liabilities or ECG's duty to pay for energy supplied (cl. 20.1.3). The plant stays with the seller after expiry or termination (cl. 20.2.3). Source: cl. 19.3.2; 20.1.3; 20.2.3 (p. 19-20)
Dispute resolution
- Governing law
- Laws of Ghana Source: cl. 29 (p. 23)
- Dispute resolution: negotiation / mediation
- Yes Source: cl. 22.1 (p. 20)
- Dispute resolution: expert determination
- No
- Dispute resolution: arbitration
- Yes Source: cl. 22.2 (p. 20-21)
- Dispute resolution: court proceedings
- No
- Dispute resolution: other
- No
- Arbitration seat
- London, England Source: cl. 22.2.3 (p. 21)
- Applicable arbitration rules
- London Court of International Arbitration (LCIA); 3 arbitrators; English language Source: cl. 22.2.1-22.2.3 (p. 20-21)
Amendments
- Number of amendments executed
- Not in contract (base PPA only; no amendments in the set provided) Source: cl. 24.1 (p. 21)