← Back to contracts

GH-PPA-10

Safi Sana 100 kW Waste-to-Energy (Biogas CHP) Plant, Ashaiman

Safi Sana Ghana Limited · Waste-to-Energy · 0.10 MW · Ashaiman, Ashaiman Municipality, Greater Accra Region, Ghana

Summary

A 100 kW waste-to-energy (biogas CHP) plant in Ashaiman, supplying ECG under a 15-year energy-only PPA (the signing date was left blank in the executed copy; year 2016). A flat feed-in tariff of 17.51 US cents/kWh applies for 10 years from commercial operation, 80% USD-denominated, with a take-or-pay obligation.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
—
Financial close
Not stated
Commercial operation
Scheduled COD is 21 months after the Target Effective Date (itself 12 months after the Signature Date); Long Stop COD is 3 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Schedule 6 illustrates this as Signing +12mo -> Target Effectiveness +3mo -> Long Stop Effective +18mo -> Scheduled COD +3mo -> Long Stop COD. Source: 'Scheduled Commercial Operations Date', 'Target Effective Date' definitions; cl. 6.3; Sch. 6 (p. 12; 9-10; 17; 43)
Contract end
The 15th anniversary of the Commercial Operation Date (defined 'End Date'), consistent with the 15-year Term stated in cl. 4 Source: 'End Date' definition; cl. 4 (p. 9; 15)
Contract duration
15 years
Contract status
Active
Project status
Not recorded
Tariff structure
Energy-only
Capacity charge
None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 18)
Energy charge
USD 0.1751/kWh
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Feed-In-Tariff fixed at 17.51 US cents/kWh from commercial operation to the 10th anniversary; thereafter reset every two years with PURC approval, no stated formula. 80% of the tariff is USD-denominated and paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC; the remaining 20% local-cost component is billed and paid directly in Cedis.
Project overview
Installed capacity (MW)
100 kW (Nameplate Capacity) Source: Preamble; 'Contracted Capacity' definition (p. 6; 8)
Commercial operation date (COD)
Scheduled COD is 21 months after the Target Effective Date (itself 12 months after the Signature Date); Long Stop COD is 3 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Schedule 6 illustrates this as Signing +12mo -> Target Effectiveness +3mo -> Long Stop Effective +18mo -> Scheduled COD +3mo -> Long Stop COD. Source: 'Scheduled Commercial Operations Date', 'Target Effective Date' definitions; cl. 6.3; Sch. 6 (p. 12; 9-10; 17; 43)
PPA expiry
The 15th anniversary of the Commercial Operation Date (defined 'End Date'), consistent with the 15-year Term stated in cl. 4 Source: 'End Date' definition; cl. 4 (p. 9; 15)
Contract term (years)
15 Source: cl. 4; 'End Date', 'Term' definitions (p. 9; 15)
Contracting parties
Transmission service provider
Not applicable as a separate transmission utility; the Facility connects to the Buyer's own 33kV distribution network (embedded generation), not the national transmission grid Source: 'Buyer Distribution Network', 'Delivery Point' definitions; cl. 6.1 (p. 7; 9; 17)
Government support entity
Not addressed in the PPA; may be addressed in related documents.
Project sponsors / shareholders
Not in contract
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Energy-Only PPA Source: cl. 7.1-7.2 (p. 18)
Contracted capacity (MW)
100 kW (Contracted Capacity, nameplate) Source: 'Contracted Capacity' definition (p. 8)
Tariff currency
US Dollars for 80% of the tariff (paid in Cedis via a quarterly Hedged Exchange Rate); Ghana Cedis directly for the remaining 20% local-cost component Source: cl. 7.2; 10.4(e) (p. 18; 22)
Tariff structure summary
Flat Feed-In-Tariff of USCents 17.51/kWh on Energy delivered, fixed from COD to the 10th anniversary of COD; thereafter adjusted every two years with PURC approval until the end of the Term. 80% of the tariff is USD-denominated (paid in Cedis at a Hedged Exchange Rate); the remaining 20% local-cost component is billed and paid directly in Cedis. Annual Energy is also banded (Minimum 632.9 MWh / Contracted 658.95 MWh / Maximum 685 MWh) with shortfall payments and an excess-energy charge outside the band. Source: 'Feed-In-Tariff' definition; cl. 7.2; 7.5-7.6; 10.4(e) (p. 10; 18-19; 22)
Capacity charge
None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 18)
Energy charge
Feed-In-Tariff (USCents 17.51/kWh to year 10) multiplied by metered Energy delivered at the Delivery Point Source: cl. 7.2 (p. 18)
Tariff escalation mechanism
No escalation for the first 10 years from COD; thereafter the Feed-In-Tariff is adjusted every two years with PURC approval, with no stated formula, cap or floor, until the end of the 15-year Term. Source: 'Feed-In-Tariff' definition (p. 10)
Indexation: inflation
No Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 10; 18)
Indexation: foreign exchange
Yes Source: cl. 7.2-7.3; 10.4(e) (p. 18; 22)
Indexation: fuel price
No Source: cl. 7.5(a) (p. 18-19)
Indexation: none / fixed tariff
Yes Source: 'Feed-In-Tariff' definition (p. 10)
Indexation: other
No Source: 'Feed-In-Tariff' definition (p. 10)
Summary of indexation methodology
Feed-In-Tariff fixed at USCents 17.51/kWh from COD to the 10th anniversary of COD; thereafter reset every two years with PURC approval, no stated formula. 80% of the tariff is USD-denominated and paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC; the remaining 20% local-cost component is billed and paid directly in Cedis. Source: 'Feed-In-Tariff' definition; cl. 7.2-7.3; 10.4(e) (p. 10; 18; 22)
Billing and payment cycle
Monthly. Seller invoices by the 10th of the following month; Buyer pays by the Due Date (45 days after invoice receipt, per the 'Due Date' definition); VAT applied on invoicing. Interest at the Default Rate (3-month US LIBOR) accrues on amounts overdue 35+ days, and the Seller may discontinue supply if unpaid 35 days after the Due Date. Source: cl. 10.1; 10.4(f); 13.4; 'Default Rate', 'Due Date' definitions (p. 9; 20-23)
Government and consumer exposure
Take-or-pay obligation
Yes Source: cl. 3.1 (p. 14)
Take-or-pay details
The Buyer must receive and purchase 100% of the Energy the Seller produces and delivers from COD, and must also pay for energy supplied during the 12-month commissioning period (cl. 3.2, 7.4). Source: cl. 3.1; 3.2; 7.4 (p. 14; 18)
Minimum offtake requirement
Yes Source: cl. 3.4; 7.5(b) (p. 14; 18-19)
Minimum offtake details
If actual Annual Energy received is below the Minimum Annual Energy (632.9 MWh) for reasons attributable to the Buyer, the Buyer must pay the Seller the shortfall multiplied by the Feed-In-Tariff (which may include gas flared for reasons attributable to the Buyer). This protection does not apply to the Seller within the first Year of the Commercial Operation Date. Source: cl. 3.4(b); 7.5(a)-(b) (p. 14; 18-19)
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 7.2-7.3; 10.4(a)-(b), (e) (p. 18; 21-22)
Foreign exchange protection details
80% of the tariff is invoiced in USD but paid to the Seller in Ghana Cedis at a Hedged Exchange Rate the Seller obtains each Quarter from a Ghanaian commercial bank and files with PURC, so ECG bears cedi depreciation on that portion; the remaining 20% local-cost component is billed and paid directly in Cedis with no conversion mechanism (cl. 10.4(e)). No reconciliation is stated for any gap between the hedge rate and the Seller's actual conversion cost, which stays with the Seller. Source: cl. 7.2-7.3; 10.4(a)-(b), (e) (p. 18; 21-22)
Other government commitments
Not addressed in the PPA; may be addressed in related documents.
Fiscal incentives and non-tariff government support
No tax holiday, duty or VAT exemption, stabilization clause, or concessional financing found; the Invoice instead applies VAT at the prevailing rate (cl. 10.1(c)). No government-funded land, interconnection or other non-tariff support identified. Source: cl. 10.1(c) (p. 20)
Risk allocation
Fuel supply risk borne by
Not addressed Source: cl. 7.5(a); Sch. 4 heading (p. 19; 40)
Resource availability risk borne by
Not addressed
Foreign exchange risk borne by
Shared Source: cl. 7.2-7.3; 10.4 (p. 18; 21-22)
Change in law risk borne by
Offtaker Source: cl. 8; 9; 27.3 (p. 19-20; 33)
Transmission and grid availability risk borne by
Not addressed
Performance obligations
Performance guarantee
Yes Source: cl. 7.5(a); 6.4-6.5 (p. 18-19; 17-18)
Curtailment compensation
Not Applicable Source: cl. 13.1 (p. 23)
Summary of curtailment arrangements
Not addressed as a distinct concept. The Seller must supply in accordance with Dispatch Instructions (cl. 13.1), but no clause ties Buyer-directed dispatch reductions to a specific payment; the only compensation mechanisms in the PPA are the Minimum/Maximum Annual Energy shortfall payment and excess-energy charge (cl. 7.5-7.6). Source: cl. 13.1; 7.5-7.6 (p. 23; 18-19)
Force majeure, default and termination
Termination compensation: seller default
Not stated Source: cl. 21.2(b) (p. 30)
Termination compensation: buyer default
Not stated Source: cl. 21.3 (p. 31)
Termination compensation: political force majeure
Not stated Source: cl. 21.4(b) (p. 31)
Summary of termination compensation framework
The PPA has no termination payment formula for any scenario. On Seller default, the Buyer's ongoing payment obligation is only reduced by an amount equivalent to the Seller's liabilities arising from the default (cl. 21.2(b)); there is no equivalent netting provision for Buyer default. Termination for prolonged Force Majeure (36 months, cl. 21.4(b)) carries no stated compensation. General indemnification for reasonable out-of-pocket losses during a default period is available under cl. 20.4. Source: cl. 20.4; 21.2(b); 21.3; 21.4(b) (p. 30-31)
Dispute resolution
Governing law
Laws of Ghana Source: cl. 23 (p. 31)
Dispute resolution: negotiation / mediation
Yes Source: cl. 24.1 (p. 32)
Dispute resolution: arbitration
Yes Source: cl. 24.2 (p. 32)
Dispute resolution: court proceedings
No
Dispute resolution: other
No
Arbitration seat
Stockholm, Sweden Source: cl. 24.2(b) (p. 32)
Applicable arbitration rules
ICC Rules of Arbitration; 3 arbitrators; English language Source: cl. 24.2(a)-(c) (p. 32)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 27.1 (p. 33)