Summary

A 20 MW solar PV plant in the Central Region, supplying ECG under a PPA signed 23 December 2015 running 20 years from commercial operation (the agreement's own term clause separately states 25 years — an internal inconsistency flagged for Ministry review). A flat feed-in tariff of 18.2464 US cents/kWh applies for the first 10 years, reset by PURC thereafter, with a take-or-pay obligation.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2015-12-23
Financial close
Not stated
Commercial operation
Scheduled COD 24 months after the Target Effective Date (itself 12 months after the Signature Date), i.e. approx. 36 months after signing; Long Stop COD 6 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Source: 'Scheduled Commercial Operation Date', 'Target Effective Date' definitions; cl. 6.3 (p. 9-10; 14)
Contract end
Not stated
Contract duration
20 years
Contract status
Active
Project status
Not recorded
Tariff structure
Energy-only
Capacity charge
None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 16)
Energy charge
USD 0.182464/kWh
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Feed-In-Tariff fixed at 18.2464 US cents/kWh for the first 10 years of the Term; from year 11 the FIT is reset 'as approved by PURC' with no stated formula. Tariff invoiced in USD, paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC.
Project overview
Installed capacity (MW)
20 (Nameplate Capacity) Source: Preamble; 'Contracted Capacity' definition (p. 4; 6)
Commercial operation date (COD)
Scheduled COD 24 months after the Target Effective Date (itself 12 months after the Signature Date), i.e. approx. 36 months after signing; Long Stop COD 6 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Source: 'Scheduled Commercial Operation Date', 'Target Effective Date' definitions; cl. 6.3 (p. 9-10; 14)
Contracting parties
Transmission service provider
Ghana Grid Company (GRIDCo), as Electricity Transmission Utility (ETU) Source: 'ETU' definition (p. 7)
Government support entity
Not addressed in the PPA; may be addressed in related documents.
Project sponsors / shareholders
Not in contract
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Energy-Only PPA Source: cl. 7.1-7.2 (p. 16)
Contracted capacity (MW)
20 (Contracted Capacity, nameplate) Source: 'Contracted Capacity' definition (p. 6)
Tariff currency
US Dollars, invoiced monthly in USD and payable in Ghana Cedis at a quarterly Hedged Exchange Rate Source: cl. 7.2; 7.3; 10.4(b) (p. 16; 19)
Tariff structure summary
Flat Feed-In-Tariff of USCents 18.2464/kWh on Energy delivered, fixed for the first 10 years of the Term; thereafter as approved by PURC. Annual Energy is also banded (Minimum 37.46 GWh / Contracted 38.68 GWh / Maximum 39.90 GWh) with shortfall payments and discounts outside the band. Source: 'Feed-In-Tariff' definition; cl. 7.2; 7.5-7.6 (p. 7; 16-17)
Capacity charge
None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 16)
Energy charge
Feed-In-Tariff (USCents 18.2464/kWh, first 10 years) multiplied by metered Energy delivered at the Delivery Point Source: cl. 7.2 (p. 16)
Tariff escalation mechanism
No escalation for the first 10 years of the Term; thereafter the Feed-In-Tariff is 'as approved by PURC' with no stated formula, cap or floor. Source: 'Feed-In-Tariff' definition (p. 7)
Indexation: inflation
No Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 7; 16)
Indexation: foreign exchange
Yes Source: cl. 7.2-7.3 (p. 16)
Indexation: fuel price
No
Indexation: none / fixed tariff
Yes Source: 'Feed-In-Tariff' definition (p. 7)
Indexation: other
No Source: 'Feed-In-Tariff' definition (p. 7)
Summary of indexation methodology
Feed-In-Tariff fixed at USCents 18.2464/kWh for the first 10 years of the Term; from year 11 the FIT is reset 'as approved by PURC' with no stated formula. Tariff invoiced in USD, paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC. Source: 'Feed-In-Tariff' definition; cl. 7.2-7.3 (p. 7; 16)
Billing and payment cycle
Monthly. Seller invoices by the 10th of the following month; Due Date is 45 days after the Buyer receives the invoice; VAT applied on invoicing. Interest at the Default Rate (0.05% above 3-month USD LIBOR) accrues after 35 days overdue, and the Seller may discontinue supply if unpaid 35 days after the Due Date. Source: cl. 10.1; 10.4(e); 12.4; 'Default Rate', 'Due Date' definitions (p. 7; 18-21)
Government and consumer exposure
Take-or-pay obligation
Yes Source: cl. 3.1 (p. 12)
Take-or-pay details
The Buyer must receive and purchase 100% of the Energy the Seller produces and delivers from COD, and must also pay for energy supplied during commissioning (cl. 7.4). A Seller-attributable shortfall below the Minimum Annual Energy (37.46 GWh) obliges the Seller to pay the Buyer's replacement-energy cost, measured against the Contracted Annual Energy (38.68 GWh) (cl. 7.5(a)). Source: cl. 3.1; 7.4; 7.5(a) (p. 12; 16)
Minimum offtake requirement
Yes Source: cl. 3.4; 7.5(b) (p. 12; 16-17)
Minimum offtake details
If actual Annual Energy received is below the Minimum Annual Energy (37.46 GWh) for reasons attributable to the Buyer, the Buyer must pay the Seller the shortfall multiplied by the Feed-In-Tariff. The same shortfall protection does not apply to the Seller in the Facility's first year of operation. Source: cl. 3.4(b); 7.5(b) (p. 12; 17)
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 7.2-7.3; 10.4(a)-(b) (p. 16; 19)
Foreign exchange protection details
The tariff is invoiced in USD but paid to the Seller in Ghana Cedis at a Hedged Exchange Rate the Seller obtains each Quarter from a Ghanaian commercial bank and files with PURC, so ECG bears cedi depreciation through the conversion. No reconciliation is stated for any gap between the hedge rate and the Seller's actual conversion cost, which stays with the Seller. Source: cl. 7.2-7.3; 10.4(a)-(b) (p. 16; 19)
Other government commitments
Not addressed in the PPA; may be addressed in related documents.
Fiscal incentives and non-tariff government support
No tax holiday, duty or VAT exemption, stabilization clause, or concessional financing found; the Invoice instead applies VAT at the prevailing rate (cl. 10.1(c)). No government-funded land, interconnection or other non-tariff support identified. Source: cl. 10.1(c) (p. 18)
Risk allocation
Fuel supply risk borne by
Not applicable
Resource availability risk borne by
Seller Source: cl. 6.4; 7.5(a); 13.1; 'Natural Event' definition (p. 14-15; 16-17; 21; 9)
Foreign exchange risk borne by
Shared Source: cl. 7.2-7.3; 10.4 (p. 16; 19)
Change in law risk borne by
Offtaker Source: cl. 8; 9; 26.3 (p. 17-18; 31-32)
Transmission and grid availability risk borne by
Not addressed
Performance obligations
Performance guarantee
Yes Source: cl. 6.4-6.5; 7.5 (p. 15; 16-17)
Summary of performance obligations
Liquidated damages of US$5,000/day payable by the Seller for late COD, secured by a US$500,000 Performance Bond and a separate US$500,000 Development Bond for delay to the Effective Date. Output performance is enforced through the Minimum/Maximum Annual Energy band: a Seller-caused shortfall below 37.46 GWh is paid by the Seller at the Buyer's replacement cost, measured against the Contracted Annual Energy of 38.68 GWh; excess above 39.90 GWh earns the Buyer a 50%-of-tariff discount. Seller default threshold: less than 95% of the corresponding portion of the Minimum Annual Energy over any continuous 180 days (cl. 19.1). Source: cl. 5.5; 6.4-6.5; 7.5-7.6; 19.1 (p. 14; 15; 16-17; 27)
Curtailment compensation
Not Applicable Source: cl. 12.1; 12.3 (p. 21)
Summary of curtailment arrangements
Not addressed as a distinct concept. The Seller must supply in accordance with ETU/GRIDCo Dispatch Instructions (cl. 12.1) and may be instructed by the Buyer under the Grid Code or Connection Agreement to discontinue supply (cl. 12.3(b)), with no stated compensation; no clause ties Buyer-directed dispatch reductions to a specific payment. The only compensation mechanisms in the PPA are the Minimum/Maximum Annual Energy shortfall payment and discount (cl. 7.5-7.6). Source: cl. 12.1; 12.3(b); 7.5-7.6 (p. 21; 16-17)
Force majeure, default and termination
Termination compensation: seller default
Not stated Source: cl. 20.2(b) (p. 28)
Termination compensation: buyer default
Not stated Source: cl. 20.3 (p. 28)
Termination compensation: political force majeure
Not stated Source: cl. 20.4(b) (p. 28-29)
Summary of termination compensation framework
The PPA has no termination payment formula for any scenario. On Seller default, the Buyer's ongoing payment obligation is only reduced by an amount equivalent to the Seller's liabilities arising from the default (cl. 20.2(b)); there is no equivalent netting provision for Buyer default. Termination for prolonged Force Majeure (36 months, cl. 20.4(b)) carries no stated compensation. General indemnification for reasonable out-of-pocket losses during a default period is available under cl. 19.4. Source: cl. 19.4; 20.2(b); 20.3; 20.4(b) (p. 28-29)
Dispute resolution
Governing law
Laws of Ghana Source: cl. 22 (p. 29)
Dispute resolution: negotiation / mediation
Yes Source: cl. 23.1 (p. 29)
Dispute resolution: arbitration
Yes Source: cl. 23.2 (p. 29-30)
Dispute resolution: court proceedings
No
Dispute resolution: other
No
Arbitration seat
Stockholm, Sweden Source: cl. 23.2(b) (p. 30)
Applicable arbitration rules
ICC Rules of Arbitration; 3 arbitrators; English language Source: cl. 23.2(a)-(c) (p. 30)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 26.1 (p. 31)