GH-PPA-DRAFT-09

Meinergy 20 MW Solar PV Project, Central Region

Meinergy Technology Limited · Solar PV · 20.00 MW · Central Region, Ghana

Summary

A 20 MW solar PV plant in the Central Region, supplying ECG under a PPA signed 23 December 2015 running 20 years from commercial operation (the agreement's own term clause separately states 25 years — an internal inconsistency flagged for Ministry review). A flat feed-in tariff of 18.2464 US cents/kWh applies for the first 10 years, reset by PURC thereafter, with a take-or-pay obligation.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2015-12-23
Financial close
—
Commercial operation
—
Contract end
—
Contract duration
20 years
Contract status
Active
Tariff structure
Energy-only
Capacity charge
—
Energy charge
USD 18.2464/kWh
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Feed-In-Tariff fixed at 18.2464 US cents/kWh for the first 10 years of the Term; from year 11 the FIT is reset 'as approved by PURC' with no stated formula. Tariff invoiced in USD, paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC.