GH-PPA-09
Meinergy 20 MW Solar PV Project, Central Region
Meinergy Technology Limited · Solar PV · 20.00 MW · Central Region, Ghana
GH-PPA-09
Meinergy 20 MW Solar PV Project, Central Region
Meinergy Technology Limited · Solar PV · 20.00 MW · Central Region, Ghana
Summary
A 20 MW solar PV plant in the Central Region, supplying ECG under a PPA signed 23 December 2015 running 20 years from commercial operation (the agreement's own term clause separately states 25 years — an internal inconsistency flagged for Ministry review). A flat feed-in tariff of 18.2464 US cents/kWh applies for the first 10 years, reset by PURC thereafter, with a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2015-12-23
- Financial close
- Not stated
- Commercial operation
- Scheduled COD 24 months after the Target Effective Date (itself 12 months after the Signature Date), i.e. approx. 36 months after signing; Long Stop COD 6 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Source: 'Scheduled Commercial Operation Date', 'Target Effective Date' definitions; cl. 6.3 (p. 9-10; 14)
- Contract end
- Not stated
- Contract duration
- 20 years
- Contract status
- Active
- Project status
- Not recorded
- Tariff structure
- Energy-only
- Capacity charge
- None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 16)
- Energy charge
- USD 0.182464/kWh
- Key risk features
- Take-or-pay Currency indexation Change-in-law protection
- Indexation formula
- Feed-In-Tariff fixed at 18.2464 US cents/kWh for the first 10 years of the Term; from year 11 the FIT is reset 'as approved by PURC' with no stated formula. Tariff invoiced in USD, paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC.
Project overview
- Installed capacity (MW)
- 20 (Nameplate Capacity) Source: Preamble; 'Contracted Capacity' definition (p. 4; 6)
- Commercial operation date (COD)
- Scheduled COD 24 months after the Target Effective Date (itself 12 months after the Signature Date), i.e. approx. 36 months after signing; Long Stop COD 6 months after that. Actual COD occurs within 5 Working Days of a Commissioning Test Report confirming capacity (cl. 6.3). Source: 'Scheduled Commercial Operation Date', 'Target Effective Date' definitions; cl. 6.3 (p. 9-10; 14)
Contracting parties
- Transmission service provider
- Ghana Grid Company (GRIDCo), as Electricity Transmission Utility (ETU) Source: 'ETU' definition (p. 7)
- Government support entity
- Not addressed in the PPA; may be addressed in related documents.
- Project sponsors / shareholders
- Not in contract
- Ultimate beneficial owner(s)
- Not in contract
Commercial terms
- Contract type
- Energy-Only PPA Source: cl. 7.1-7.2 (p. 16)
- Contracted capacity (MW)
- 20 (Contracted Capacity, nameplate) Source: 'Contracted Capacity' definition (p. 6)
- Tariff currency
- US Dollars, invoiced monthly in USD and payable in Ghana Cedis at a quarterly Hedged Exchange Rate Source: cl. 7.2; 7.3; 10.4(b) (p. 16; 19)
- Tariff structure summary
- Flat Feed-In-Tariff of USCents 18.2464/kWh on Energy delivered, fixed for the first 10 years of the Term; thereafter as approved by PURC. Annual Energy is also banded (Minimum 37.46 GWh / Contracted 38.68 GWh / Maximum 39.90 GWh) with shortfall payments and discounts outside the band. Source: 'Feed-In-Tariff' definition; cl. 7.2; 7.5-7.6 (p. 7; 16-17)
- Capacity charge
- None (no separate capacity charge) Source: cl. 7.1-7.2 (p. 16)
- Energy charge
- Feed-In-Tariff (USCents 18.2464/kWh, first 10 years) multiplied by metered Energy delivered at the Delivery Point Source: cl. 7.2 (p. 16)
- Tariff escalation mechanism
- No escalation for the first 10 years of the Term; thereafter the Feed-In-Tariff is 'as approved by PURC' with no stated formula, cap or floor. Source: 'Feed-In-Tariff' definition (p. 7)
- Indexation: inflation
- No Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 7; 16)
- Indexation: foreign exchange
- Yes Source: cl. 7.2-7.3 (p. 16)
- Indexation: fuel price
- No
- Indexation: none / fixed tariff
- Yes Source: 'Feed-In-Tariff' definition (p. 7)
- Indexation: other
- No Source: 'Feed-In-Tariff' definition (p. 7)
- Summary of indexation methodology
- Feed-In-Tariff fixed at USCents 18.2464/kWh for the first 10 years of the Term; from year 11 the FIT is reset 'as approved by PURC' with no stated formula. Tariff invoiced in USD, paid in Cedis at a quarterly Hedged Exchange Rate filed with PURC. Source: 'Feed-In-Tariff' definition; cl. 7.2-7.3 (p. 7; 16)
- Billing and payment cycle
- Monthly. Seller invoices by the 10th of the following month; Due Date is 45 days after the Buyer receives the invoice; VAT applied on invoicing. Interest at the Default Rate (0.05% above 3-month USD LIBOR) accrues after 35 days overdue, and the Seller may discontinue supply if unpaid 35 days after the Due Date. Source: cl. 10.1; 10.4(e); 12.4; 'Default Rate', 'Due Date' definitions (p. 7; 18-21)
Government and consumer exposure
- Take-or-pay obligation
- Yes Source: cl. 3.1 (p. 12)
- Take-or-pay details
- The Buyer must receive and purchase 100% of the Energy the Seller produces and delivers from COD, and must also pay for energy supplied during commissioning (cl. 7.4). A Seller-attributable shortfall below the Minimum Annual Energy (37.46 GWh) obliges the Seller to pay the Buyer's replacement-energy cost, measured against the Contracted Annual Energy (38.68 GWh) (cl. 7.5(a)). Source: cl. 3.1; 7.4; 7.5(a) (p. 12; 16)
- Minimum offtake requirement
- Yes Source: cl. 3.4; 7.5(b) (p. 12; 16-17)
- Minimum offtake details
- If actual Annual Energy received is below the Minimum Annual Energy (37.46 GWh) for reasons attributable to the Buyer, the Buyer must pay the Seller the shortfall multiplied by the Feed-In-Tariff. The same shortfall protection does not apply to the Seller in the Facility's first year of operation. Source: cl. 3.4(b); 7.5(b) (p. 12; 17)
- Government guarantee
- No
- Letter of support
- No
- Foreign exchange protection mechanism
- Yes Source: cl. 7.2-7.3; 10.4(a)-(b) (p. 16; 19)
- Foreign exchange protection details
- The tariff is invoiced in USD but paid to the Seller in Ghana Cedis at a Hedged Exchange Rate the Seller obtains each Quarter from a Ghanaian commercial bank and files with PURC, so ECG bears cedi depreciation through the conversion. No reconciliation is stated for any gap between the hedge rate and the Seller's actual conversion cost, which stays with the Seller. Source: cl. 7.2-7.3; 10.4(a)-(b) (p. 16; 19)
- Other government commitments
- Not addressed in the PPA; may be addressed in related documents.
- Fiscal incentives and non-tariff government support
- No tax holiday, duty or VAT exemption, stabilization clause, or concessional financing found; the Invoice instead applies VAT at the prevailing rate (cl. 10.1(c)). No government-funded land, interconnection or other non-tariff support identified. Source: cl. 10.1(c) (p. 18)
Risk allocation
- Fuel supply risk borne by
- Not applicable
- Resource availability risk borne by
- Seller Source: cl. 6.4; 7.5(a); 13.1; 'Natural Event' definition (p. 14-15; 16-17; 21; 9)
- Foreign exchange risk borne by
- Shared Source: cl. 7.2-7.3; 10.4 (p. 16; 19)
- Change in law risk borne by
- Offtaker Source: cl. 8; 9; 26.3 (p. 17-18; 31-32)
- Transmission and grid availability risk borne by
- Not addressed
Performance obligations
- Performance guarantee
- Yes Source: cl. 6.4-6.5; 7.5 (p. 15; 16-17)
- Summary of performance obligations
- Liquidated damages of US$5,000/day payable by the Seller for late COD, secured by a US$500,000 Performance Bond and a separate US$500,000 Development Bond for delay to the Effective Date. Output performance is enforced through the Minimum/Maximum Annual Energy band: a Seller-caused shortfall below 37.46 GWh is paid by the Seller at the Buyer's replacement cost, measured against the Contracted Annual Energy of 38.68 GWh; excess above 39.90 GWh earns the Buyer a 50%-of-tariff discount. Seller default threshold: less than 95% of the corresponding portion of the Minimum Annual Energy over any continuous 180 days (cl. 19.1). Source: cl. 5.5; 6.4-6.5; 7.5-7.6; 19.1 (p. 14; 15; 16-17; 27)
- Curtailment compensation
- Not Applicable Source: cl. 12.1; 12.3 (p. 21)
- Summary of curtailment arrangements
- Not addressed as a distinct concept. The Seller must supply in accordance with ETU/GRIDCo Dispatch Instructions (cl. 12.1) and may be instructed by the Buyer under the Grid Code or Connection Agreement to discontinue supply (cl. 12.3(b)), with no stated compensation; no clause ties Buyer-directed dispatch reductions to a specific payment. The only compensation mechanisms in the PPA are the Minimum/Maximum Annual Energy shortfall payment and discount (cl. 7.5-7.6). Source: cl. 12.1; 12.3(b); 7.5-7.6 (p. 21; 16-17)
Force majeure, default and termination
- Termination compensation: seller default
- Not stated Source: cl. 20.2(b) (p. 28)
- Termination compensation: buyer default
- Not stated Source: cl. 20.3 (p. 28)
- Termination compensation: political force majeure
- Not stated Source: cl. 20.4(b) (p. 28-29)
- Summary of termination compensation framework
- The PPA has no termination payment formula for any scenario. On Seller default, the Buyer's ongoing payment obligation is only reduced by an amount equivalent to the Seller's liabilities arising from the default (cl. 20.2(b)); there is no equivalent netting provision for Buyer default. Termination for prolonged Force Majeure (36 months, cl. 20.4(b)) carries no stated compensation. General indemnification for reasonable out-of-pocket losses during a default period is available under cl. 19.4. Source: cl. 19.4; 20.2(b); 20.3; 20.4(b) (p. 28-29)
Dispute resolution
- Governing law
- Laws of Ghana Source: cl. 22 (p. 29)
- Dispute resolution: negotiation / mediation
- Yes Source: cl. 23.1 (p. 29)
- Dispute resolution: arbitration
- Yes Source: cl. 23.2 (p. 29-30)
- Dispute resolution: court proceedings
- No
- Dispute resolution: other
- No
- Arbitration seat
- Stockholm, Sweden Source: cl. 23.2(b) (p. 30)
- Applicable arbitration rules
- ICC Rules of Arbitration; 3 arbitrators; English language Source: cl. 23.2(a)-(c) (p. 30)
Amendments
- Number of amendments executed
- Not in contract (base PPA only; no amendments in the set provided) Source: cl. 26.1 (p. 31)