← Back to contracts

GH-PPA-DRAFT-07

Global Innovative Consulting 20 MW Solar PV Project, Gushei

Global Innovative Consulting Company Limited · Solar PV · 20.00 MW · Gushei, Tamale district, Northern Region, Ghana

Summary

A 20 MW solar PV plant in Gushei, Northern Region, supplying ECG under a 20-year energy-only PPA signed 24 July 2015. A flat PURC-approved feed-in tariff of 18.2464 US cents/kWh applies for the full term, with a take-or-pay obligation. Change-in-law risk is borne by ECG.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2015-07-24
Financial close
—
Commercial operation
—
Contract end
—
Contract duration
20 years
Contract status
Active
Tariff structure
Energy-only
Capacity charge
—
Energy charge
USD 18.2464/kWh
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Flat Feed-in-Tariff of 18.2464 US cents/kWh, fixed for the full 20-year Term; no CPI or fuel-price indexation (solar). USD tariff paid in Cedis via a Seller-sourced Hedged Exchange Rate, reviewed quarterly in line with PURC's quarterly automatic tariff adjustments.