Global Innovative Consulting 20 MW Solar PV Project, Gushei

Global Innovative Consulting Company Limited · Solar PV · 20.00 MW · Gushei, Tamale district, Northern Region, Ghana

Summary

A 20 MW solar PV plant in Gushei, Northern Region, supplying ECG under a 20-year energy-only PPA signed 24 July 2015. A flat PURC-approved feed-in tariff of 18.2464 US cents/kWh applies for the full term, with a take-or-pay obligation. Change-in-law risk is borne by ECG.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2015-07-24
Financial close
Not stated
Commercial operation
Scheduled Commercial Operation Date: 3 years after the Effective Date Source: 'Scheduled Commercial Operation Date' definition (p. 10)
Contract end
20 years from the Commercial Operation Date (the End Date, defined as the last day of the 20th anniversary of COD) Source: cl. 4; 'Term' and 'End Date' definitions (p. 13; 11; 7)
Contract duration
20 years
Contract status
Active
Project status
Not recorded
Tariff structure
Energy-only
Capacity charge
None (no separate capacity payment; the Feed-in-Tariff is a single flat energy rate) Source: cl. 7.2 (p. 15)
Energy charge
USD 0.182464/kWh
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Flat Feed-in-Tariff of 18.2464 US cents/kWh, fixed for the full 20-year Term; no CPI or fuel-price indexation (solar). USD tariff paid in Cedis via a Seller-sourced Hedged Exchange Rate, reviewed quarterly in line with PURC's quarterly automatic tariff adjustments.
Project overview
Expected annual generation
38.28 GWh (average annual energy, Schedule 4 / cl. 3.4) Source: cl. 3.4; Sch. 4 (p. 12; 39)
Commercial operation date (COD)
Scheduled Commercial Operation Date: 3 years after the Effective Date Source: 'Scheduled Commercial Operation Date' definition (p. 10)
PPA expiry
20 years from the Commercial Operation Date (the End Date, defined as the last day of the 20th anniversary of COD) Source: cl. 4; 'Term' and 'End Date' definitions (p. 13; 11; 7)
Contract term (years)
20 Source: cl. 4; 'Term' definition (p. 13; 11)
Contracting parties
Transmission service provider
Electricity Transmission Utility (ETU), interchangeable with Ghana Grid Company (GRIDCo) until ETU's separation under Ghanaian law Source: 'Electricity Transmission Utility (ETU)' definition (p. 7)
Government support entity
Not addressed in the PPA; may be addressed in related documents.
Project sponsors / shareholders
Not stated in the PPA
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Energy-Only PPA Source: cl. 7.2 (p. 15)
Tariff currency
US Dollars, invoiced monthly in USD and payable in Ghana Cedis at a Seller-arranged Hedged Exchange Rate Source: cl. 7.2 (p. 15)
Tariff structure summary
Single flat Feed-in-Tariff of US 18.2464 cents/kWh (PURC-approved), applied to all metered Energy delivered to the Buyer at the Delivery Point. No separate capacity charge and no tariff reset built into the 20-year Term. Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 7; 15)
Capacity charge
None (no separate capacity payment; the Feed-in-Tariff is a single flat energy rate) Source: cl. 7.2 (p. 15)
Energy charge
US 18.2464 cents/kWh (Feed-in-Tariff, PURC-approved) on metered Energy delivered to the Buyer at the Delivery Point Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 7; 15)
Tariff escalation mechanism
No escalation or reset mechanism found; the Feed-in-Tariff is fixed at 18.2464 US cents/kWh for the whole 20-year Term. Only the Hedged Exchange Rate used to convert USD invoices into Cedis is reviewed quarterly. Source: cl. 7.3 (p. 15-16)
Indexation: inflation
No
Indexation: foreign exchange
Yes Source: cl. 7.3; 10.4(a)-(b) (p. 15-16; 19)
Indexation: fuel price
No
Indexation: none / fixed tariff
Yes Source: 'Feed-In-Tariff' definition; cl. 7.2 (p. 7; 15)
Indexation: other
No
Summary of indexation methodology
Flat Feed-in-Tariff of 18.2464 US cents/kWh, fixed for the full 20-year Term; no CPI or fuel-price indexation (solar). USD tariff paid in Cedis via a Seller-sourced Hedged Exchange Rate, reviewed quarterly in line with PURC's quarterly automatic tariff adjustments. Source: 'Feed-In-Tariff' definition; cl. 7.2-7.3 (p. 7; 15-16)
Billing and payment cycle
Invoice submitted by the 10th of the month following delivery; VAT applied on invoicing. Due Date is the 45th day after the Invoice is received. Buyer may dispute before the Due Date, or within 90 days of it if it later finds an error. Payment due in Ghana Cedis at the Hedged Exchange Rate. Interest at the Default Rate (0.1 percentage point above 3-month US LIBOR) accrues once a payment is 35+ days overdue; Seller may suspend supply once unpaid 35 days and the Bank Guarantee fails to cover the shortfall. Buyer must maintain a US$1,500,000 Bank Guarantee from COD, assignable by the Seller to its Lenders. Source: cl. 10.1-10.4; 11.1-11.3; 13.4; 'Due Date' definition (p. 7; 18-20)
Government and consumer exposure
Take-or-pay obligation
Yes Source: cl. 7.5 (p. 16)
Take-or-pay details
If actual Annual Energy delivered is below the Minimum Annual Energy (37.45 GWh) for reasons attributable to the Seller, the Seller pays the Buyer the actual cost of replacement energy purchased at the system marginal price or spot market, measured against the Contracted Annual Energy of 38.28 GWh. If attributable to the Buyer, the Buyer pays the Seller the shortfall (below the Minimum Annual Energy) multiplied by the Feed-in-Tariff. The first Year of operation is exempted, and the Seller may receive projected monthly shortfall payments based on historical delivery. Source: cl. 7.5; 3.4(b) (p. 16; 12)
Minimum offtake requirement
Yes Source: cl. 7.5; Sch. 4 (p. 16; 39)
Minimum offtake details
Minimum Annual Energy of 37.45 GWh/year (Schedule 4, at 92% availability); shortfall attributable to the Buyer triggers a payment at row 41's formula; shortfall attributable to the Seller shifts replacement-power cost to the Seller instead. Energy above the Maximum Annual Energy (39.53 GWh) triggers a Discount to the Buyer equal to the excess multiplied by 50% of the Feed-in-Tariff. Source: cl. 7.5-7.6; Sch. 4 (p. 16-17; 39)
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 7.3; 10.4(a)-(b) (p. 15-16; 19)
Foreign exchange protection details
Each Quarter (after the first Year) the Seller enters an Exchange Rate Hedge Agreement with a reputable Ghanaian commercial bank at the most competitive available rate; the rate is communicated to PURC and, if acceptable, used to convert the Buyer's Cedi payment. Reviewed quarterly in line with PURC's automatic tariff adjustments. Source: cl. 7.3 (p. 15-16)
Other government commitments
PURC must issue an indicative tariff (CP for both parties, cl. 5.1(e)/5.2(c)); the Feed-in-Tariff itself is PURC-approved; Energy Commission construction permit and O&M consent are CPs (cl. 5.1(f)-(g)); the Seller is separately licensed by the Energy Commission (License No. EC/GWSL/02-14-033, Recital). No Government Consent and Support Agreement or equivalent Government-support CP was found, unlike Chrispod's PPA in this same batch. Source: cl. 5.1(e)-(g); 5.2(c); Recital (p. 13-14; 4)
Fiscal incentives and non-tariff government support
None found. Invoices apply VAT rather than being exempted from it (cl. 10.1(c)); no tax holiday, duty exemption, or stabilization clause was found in the PPA. Source: cl. 10.1(c) (p. 18)
Risk allocation
Fuel supply risk borne by
Not applicable
Resource availability risk borne by
Seller Source: cl. 7.5(a); 13.1; 'Availability' definition (p. 16; 21; 5)
Foreign exchange risk borne by
Shared Source: cl. 7.2; 10.4(a)-(b) (p. 15; 19)
Change in law risk borne by
Offtaker Source: cl. 8.1-8.3 (p. 17)
Transmission and grid availability risk borne by
Not addressed Source: 'Availability' definition (p. 5)
Summary of key risk allocation provisions
Fuel risk not applicable (solar). Resource/output risk sits with the Seller, which must deliver 'under favourable climatic conditions' and bears the cost when a delivery shortfall is attributable to it. FX: the tariff is invoiced in USD and paid in cedis at the Seller-arranged Hedged Exchange Rate, so FX risk is shared: the Buyer bears cedi depreciation, and any spread between the hedge rate and the Seller's actual conversion cost stays with the Seller. Change in Law/Increased Costs: passed to the Buyer through a tariff adjustment, but recovery requires PURC approval. Transmission/grid availability risk is not addressed anywhere in the PPA. Source: cl. 7.2-7.3; 7.5; 8; 13.1 (p. 15-17; 21)
Performance obligations
Availability requirement
No explicit availability percentage. The Seller is deemed to have defaulted if, over any continuous 180 days, the aggregate energy supplied is below 95% of the corresponding portion of the Minimum Annual Energy, or the actual annually supplied energy is below 95% of the Annual Energy. Source: cl. 20.1 (p. 27-28)
Performance guarantee
Yes Source: cl. 7.5(a); 6.4-6.5 (p. 16; 15)
Summary of performance obligations
Seller is in default if delivered energy falls below the 95% thresholds at row 59. Ongoing performance: a Seller-attributable shortfall below the Minimum Annual Energy (37.45 GWh) makes the Seller pay the Buyer's replacement-energy cost, measured against the Contracted Annual Energy (38.28 GWh) (cl. 7.5(a)). A US$1,000,000 Performance Bond secures liquidated damages of US$10,000/day for COD delay against the Scheduled Commercial Operation Date (3 years after the Effective Date); the Bond is released three months after commissioning. Insurance obligations under Section 15 mirror international IPP practice and require Lenders to be named as additional insured. Source: cl. 6.4-6.5; 15; 20.1 (p. 15; 23-24; 27-28)
Curtailment compensation
Not Applicable
Summary of curtailment arrangements
No dedicated curtailment/compensation clause. The Seller may be instructed by GRIDCo/ETU, under the Grid Code or Connection Agreement, to discontinue supply (cl. 13.3(b)) with no stated compensation for that discontinuance. Under- or over-delivery against the Minimum/Maximum Annual Energy figures is instead addressed through the compensation and discount formulas at rows 40-43. Source: cl. 13.3(b); 7.5-7.6 (p. 21; 16-17)
Force majeure, default and termination
Force majeure provisions
A Force Majeure Event is defined narrowly as a 'Natural Event' only: acts of God, epidemic/plague, or explosion/chemical contamination other than from a Political Event. War, invasion, expropriation and similar political acts are defined separately as a 'Political Event', which feeds only into the Increased Costs mechanism (Section 8), not Force Majeure relief. The Affected Party must notify within 7 days and report progress. The Buyer must still pay for Energy delivered during a Seller Force Majeure Event and cannot claim Force Majeure for its own payment obligations. A Force Majeure Event continuing 36 consecutive months, rendering Seller delivery impossible, gives either party a termination right. Source: cl. 14.1-14.5; 21.4(b); 'Natural Event' and 'Political Event' definitions (p. 9; 21-23; 29)
Termination compensation: seller default
Not stated Source: cl. 20.4; 21.2(b) (p. 28-29)
Termination compensation: buyer default
Not stated Source: cl. 20.4 (p. 28)
Termination compensation: political force majeure
Not stated Source: cl. 21.4(b) (p. 29)
Summary of termination compensation framework
No termination payment formula is found anywhere in the PPA. On either party's default, the non-defaulting party may seek indemnification and compensation for reasonable out-of-pocket losses incurred during the default period (cl. 20.4), with no formula or cap specified. The Buyer remains liable to pay for Energy actually supplied even on Seller default, net of the Seller's liabilities resulting from that default (cl. 21.2(b)). Political Event is not a Force Majeure trigger, and the 36-month Force Majeure termination right (cl. 21.4(b)) carries no associated payment. On termination, the Seller may remove its non-fixture equipment from the site (cl. 21.5). Source: cl. 20.4; 21.2(b); 21.4(b); 21.5 (p. 28-29)
Dispute resolution
Governing law
Laws of Ghana Source: cl. 23 (p. 29)
Dispute resolution: negotiation / mediation
Yes Source: cl. 24.1 (p. 29)
Dispute resolution: arbitration
Yes Source: cl. 24.2 (p. 30)
Dispute resolution: court proceedings
No
Dispute resolution: other
No
Arbitration seat
Stockholm, Sweden Source: cl. 24.2(b) (p. 30)
Applicable arbitration rules
ICC Rules of Arbitration; 3 arbitrators (one appointed by each party, who select the chair, or the ICC Court decides); English language Source: cl. 24.2(a)-(c) (p. 30)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 27.1; 27.4 (p. 31-32)