GH-PPA-06

Chrispod 350 MW Dual-Fuel Combined Cycle Power Plant, Aboadze

Chrispod Hydro Power Limited · Thermal (Gas) · 350.00 MW · Aboadze, Western Region, Ghana

Summary

A 350 MW dual-fuel combined-cycle plant in Aboadze, supplying ECG under a capacity-and-energy PPA signed 13 October 2014 running 20 years from commercial operation. The tariff combines a fixed per-kWh capacity charge with a gas-price-linked energy charge, and a take-or-pay obligation. Change-in-law risk is borne by ECG.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2014-10-13
Financial close
Not stated
Commercial operation
28 months after the Effective Date (Scheduled Commercial Operation Date) Source: 'Scheduled Commercial Operation Date' definition; Sch. 3 (p. 12; 41)
Contract end
Not stated
Contract duration
20 years
Contract status
Active
Project status
Not recorded
Tariff structure
Capacity + Energy
Capacity charge
Unit Capacity Charge (embedded in the per-kWh tariff, not a stand-alone MW payment): Fixed Capacity Charge 0.0340 US$/kWh plus Variable Capacity Charge 0.0234 US$/kWh, applied to Electricity generated at the Delivery Point. Source: cl. 7.2(a) (p. 17)
Energy charge
Unit Energy Charge = 0.007342 (contracted heat rate, MMBTU/kWh) x Actual Natural Gas Price (US$/MMBTU), fixed quarterly through the Gas Supply Agreement and passed through the tariff by PURC. A blended formula applies for light crude oil or a gas/oil mix. Source: cl. 7.2(b); 7.3 (p. 17-18)
Key risk features
Take-or-pay Currency indexation Change-in-law protection
Indexation formula
Capacity Charge components (0.0340 + 0.0234 US$/kWh) fixed for the Term, no CPI escalation. Energy Charge tracks the actual natural gas price, fixed quarterly under the Gas Supply Agreement and passed through the tariff by PURC. USD tariff paid in Cedis via a Seller-sourced quarterly Hedged Exchange Rate communicated to and accepted by PURC.
Project overview
Expected annual generation
2,639 GWh (annualised average, Schedule 4) Source: cl. 3.4; Sch. 4 (p. 14; 42)
Commercial operation date (COD)
28 months after the Effective Date (Scheduled Commercial Operation Date) Source: 'Scheduled Commercial Operation Date' definition; Sch. 3 (p. 12; 41)
Contracting parties
Transmission service provider
Ghana Grid Company Limited (GRIDCo) Source: 'GRIDCo' definition; 'Delivery Point' definition; cl. 13.3(b) (p. 10; 8; 24)
Government support entity
Not named in the PPA. The Seller must obtain a separate 'Government Consent and Support Agreement' with the Government as a condition precedent to the Seller's obligations; the terms of that agreement are not part of this PPA. Source: cl. 5.1(b); 'Government Consent and Support Agreement' definition (p. 14; 10)
Project sponsors / shareholders
Not stated in the PPA
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Capacity and Energy PPA Source: cl. 7.1-7.2 (p. 17)
Contracted capacity (MW)
350 (Facility installed capacity); the PPA does not define a separate 'Contracted Capacity' figure Source: 'Facility' definition; 'Capacity' definition (p. 9; 7)
Tariff currency
US Dollars, invoiced monthly in USD and payable in Ghana Cedis at a Seller-arranged Hedged Exchange Rate Source: cl. 7.5; 10.4(b) (p. 18; 22)
Tariff structure summary
Total Energy Charge = Tariff (US$/kWh) x Energy generated (kWh). Tariff = Unit Capacity Charge (Fixed 0.0340 US$/kWh plus Variable 0.0234 US$/kWh) + Unit Energy Charge (0.007342 x actual gas price, US$/MMBTU). A separate blended formula applies when fuelled by light crude oil or a gas/oil mix. Plus an Excess Starts Charge of US$3,000 per start beyond 50 starts/year. Source: cl. 7.2-7.3; 7.8 (p. 17-18)
Capacity charge
Unit Capacity Charge (embedded in the per-kWh tariff, not a stand-alone MW payment): Fixed Capacity Charge 0.0340 US$/kWh plus Variable Capacity Charge 0.0234 US$/kWh, applied to Electricity generated at the Delivery Point. Source: cl. 7.2(a) (p. 17)
Energy charge
Unit Energy Charge = 0.007342 (contracted heat rate, MMBTU/kWh) x Actual Natural Gas Price (US$/MMBTU), fixed quarterly through the Gas Supply Agreement and passed through the tariff by PURC. A blended formula applies for light crude oil or a gas/oil mix. Source: cl. 7.2(b); 7.3 (p. 17-18)
Tariff escalation mechanism
Capacity Charge components (0.0340 + 0.0234 US$/kWh) are fixed figures with no escalation mechanism found. The Energy Charge tracks the actual gas price, adjusted quarterly and passed through the tariff via PURC. Source: cl. 7.2-7.3 (p. 17-18)
Indexation: inflation
No
Indexation: foreign exchange
Yes Source: cl. 7.4-7.5; 10.4(a)-(b) (p. 18; 22)
Indexation: fuel price
Yes Source: cl. 7.2(b)(iii) (p. 17-18)
Indexation: none / fixed tariff
No
Indexation: other
No
Summary of indexation methodology
Capacity Charge components (0.0340 + 0.0234 US$/kWh) fixed for the Term, no CPI escalation. Energy Charge tracks the actual natural gas price, fixed quarterly under the Gas Supply Agreement and passed through the tariff by PURC. USD tariff paid in Cedis via a Seller-sourced quarterly Hedged Exchange Rate communicated to and accepted by PURC. Source: cl. 7.2-7.5 (p. 17-18)
Government and consumer exposure
Take-or-pay obligation
Yes Source: cl. 7.9 (p. 18-19)
Take-or-pay details
If actual annual Energy delivered is below the Minimum Annual Energy (2,556 GWh) for reasons attributable to the Buyer, the Buyer pays an Annual Compensation = (2,556 - CB) x (0.0574 + 0.007342 x GTP) x 10^6, where GTP is the take-or-pay gas price (zero under a take-and-pay gas contract). If the shortfall is attributable to the Seller, the Seller instead pays the Buyer the cost of replacement energy purchased at the system marginal price or spot market. The annual true-up applies from the second year after COD; the first year of operation is exempted (cl. 3.4(b)). Source: cl. 7.9; 3.4(b) (p. 18-19; 14)
Minimum offtake requirement
Yes Source: cl. 7.9; Sch. 4 (p. 18-19; 42)
Minimum offtake details
Minimum Annual Energy of 2,556 GWh/year (Schedule 4); shortfall attributable to the Buyer triggers the Annual Compensation formula at row 41; shortfall attributable to the Seller shifts the replacement-power cost to the Seller instead. Exempted in the first year of operation. Source: cl. 7.9; 3.4(b); Sch. 4 (p. 18-19; 14; 42)
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 7.4-7.5; 10.4(a)-(b) (p. 18; 22)
Foreign exchange protection details
Each Quarter the Seller enters an Exchange Rate Hedge Agreement with a reputable Ghanaian commercial bank at the most competitive available rate; the rate is communicated to PURC and, if acceptable, used to convert the Buyer's Cedi payment. Protection is limited to a hedge/conversion mechanism (not a formal FX-loss indemnity). Source: cl. 7.4-7.5; 10.4(a)-(b) (p. 18; 22)
Other government commitments
PURC must issue an indicative tariff (CP for both parties, cl. 5.1(f)/5.2(c)); Energy Commission construction permit and operating licence (CP, cl. 5.1(h)); Seller must obtain a separate Government Consent and Support Agreement (CP, cl. 5.1(b), not attached). No sovereign-immunity waiver, no offshore payment mechanism, and no reference to a Ministry no-objection or PURC 'approval' beyond the indicative tariff were found. The Buyer must assist the Seller with Consents and customs and immigration procedures (cl. 12.2(d)). Source: cl. 5.1(b), (f), (h); 5.2(c); 12.2(d) (p. 14-15; 23)
Fiscal incentives and non-tariff government support
None found. Invoices apply VAT rather than being exempted from it (cl. 10.1(c)); no tax holiday, duty exemption, or stabilization clause was found in the PPA. Source: cl. 10.1(c) (p. 21)
Risk allocation
Fuel supply risk borne by
Shared Source: cl. 7.2(b); 7.9; 13.4; 'Fuel' and 'Fuel Oil/Gas Supply Agreement' definitions (p. 9; 17-19; 24)
Resource availability risk borne by
Not applicable
Foreign exchange risk borne by
Shared Source: cl. 7.5; 10.4(a)-(b) (p. 18; 22)
Change in law risk borne by
Offtaker Source: cl. 8.1-8.3 (p. 20)
Transmission and grid availability risk borne by
Not addressed Source: 'Availability' definition (p. 7)
Summary of key risk allocation provisions
Fuel: shared. The Seller procures and bears supply/delivery risk for gas and back-up light crude oil; gas price risk largely passes to the Buyer through the quarterly, PURC-approved Energy Charge and the Minimum/Maximum Annual Energy compensation mechanism. FX: the tariff is invoiced in USD and paid in Cedis at the Seller-arranged quarterly Hedged Exchange Rate, so FX risk is shared: the Buyer bears cedi depreciation, and any spread between the hedge rate and the Seller's actual conversion cost stays with the Seller. Change in Law/Increased Costs: borne by the Buyer through a tariff adjustment, but recovery requires PURC approval; if PURC declines, the cost stays with the Seller. Transmission/grid availability risk is not addressed anywhere in the PPA. Resource availability risk is not applicable (thermal plant). Source: cl. 7.2(b); 7.4-7.5; 7.9; 8; 13.4 (p. 17-22)
Performance obligations
Availability requirement
No explicit availability percentage. The Seller is deemed to have defaulted if, over any continuous 180 days, the aggregate energy supplied is below 85% of the corresponding portion of the Annual Energy, or the actual annually supplied energy is below 85% of the Annual Energy. Source: cl. 20.1 (p. 31)
Performance guarantee
Yes Source: cl. 7.9(a); 6.4-6.5 (p. 18-19; 16-17)
Curtailment compensation
Not Applicable
Summary of curtailment arrangements
No dedicated curtailment/compensation clause. The Seller may be instructed by GRIDCo, under the Grid Code or Connection Agreement, to discontinue supply (cl. 13.3(b)) with no stated compensation for that discontinuance. Under- or over-delivery against the Minimum/Maximum Annual Energy figures is instead addressed through the compensation and discount formulas at rows 40-43. Source: cl. 13.3(b); 7.9-7.10 (p. 24; 18-20)
Force majeure, default and termination
Force majeure provisions
Force Majeure covers any circumstance beyond a party's reasonable control (excluding payment obligations), including acts of war, invasion, armed conflict, terrorism, acts of God, and epidemics, occurring after the Signature Date. The Affected Party must notify within 7 days and report progress. The Buyer must still pay for Energy delivered during a Seller Force Majeure and cannot claim Force Majeure for its own payment obligations. No Force Majeure-based termination right was found anywhere in the Agreement. Source: cl. 14.1-14.5 (p. 24-26)
Termination rights
Buyer may terminate on the Seller's uncured default (85% delivery threshold, cl. 20.1/21.2). Seller may terminate, or discontinue supply without terminating, on the Buyer's uncured payment default (cl. 20.2/21.3). Either party may terminate on the other's bankruptcy/liquidation, or on a merger/asset transfer to a successor not fully committed to the Agreement's obligations (cl. 21.4). Either party may also terminate if the Conditions Precedent are not met or waived within 3 months of the Signature Date, subject to a proviso protecting a diligent Seller (cl. 5.3). Source: cl. 5.3; 20.1-20.2; 21.1-21.4 (p. 15; 31-32)
Termination compensation: seller default
Not stated Source: cl. 20.4; 21.2(b) (p. 31-32)
Termination compensation: buyer default
Not stated Source: cl. 20.4 (p. 31)
Termination compensation: political force majeure
Not stated
Summary of termination compensation framework
No termination payment formula is found anywhere in the PPA. On either party's default, the non-defaulting party may claim compensation for losses incurred during the default period (cl. 20.4), with no formula or cap specified. The Buyer remains liable to pay for Energy actually supplied even on Seller default, net of the Seller's liabilities resulting from that default (cl. 21.2(b)). There is no Force Majeure-based termination right or associated compensation category in this Agreement. Source: cl. 20.4; 21.2(b) (p. 31-32)
Dispute resolution
Governing law
Laws of Ghana Source: cl. 23 (p. 32)
Dispute resolution: negotiation / mediation
Yes Source: cl. 24.1 (p. 32)
Dispute resolution: arbitration
Yes Source: cl. 24.2 (p. 32-33)
Dispute resolution: court proceedings
No
Dispute resolution: other
No
Arbitration seat
Stockholm, Sweden Source: cl. 24.2(b) (p. 33)
Applicable arbitration rules
ICC Rules of Arbitration; 3 arbitrators (one appointed by each party, who select the chair, or the ICC Court decides); English language Source: cl. 24.2(a)-(c) (p. 32-33)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 27.1 (p. 34)