← Back to contracts

GH-PPA-04

BXC Aboadze Generation Project (378 MW Combined Cycle)

BXC Company (Ghana) Limited · Thermal (Gas) · 378.00 MW · Aboadze, Western Region, Ghana

Summary

A 378 MW (ISO) dual-fuel combined-cycle plant in Aboadze, supplying ECG under a capacity-and-energy PPA signed 5 September 2016 running 20 years from commercial operation. The tariff combines a fixed capacity charge with a fuel- and CPI-indexed energy charge, a take-or-pay obligation, and Fair-Market-Value compensation to the developer on ECG default or political force-majeure termination. Change-in-law risk is borne by ECG.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2016-09-05
Financial close
Not stated
Commercial operation
36 months after the Effective Date (Scheduled COD), or such later date as the Parties agree; Long Stop COD is 6 months after the Scheduled COD. The Effective Date itself is targeted within 12 months of the Signature Date (Scheduled Effective Date), with an 18-month Long Stop Effective Date. Source: 'Scheduled Commercial Operation Date', 'Long Stop Commercial Operation Date', 'Scheduled Effective Date', 'Long Stop Effective Date' definitions; Sch. 14 (p. 13; 11; 80)
Contract end
20 years from the Commercial Operation Date, unless earlier terminated or extended; the formal 'Term' itself begins running from the (earlier) Effective Date. After COD the Term is extended day for day for delay caused by Force Majeure, a Buyer breach or an ETU breach of the Connection Agreement (cl. 16.6(b)). Source: 'Term' definition; Sch. 14; cl. 16.6(b) (p. 14; 80; 32)
Contract duration
20 years
Contract status
Active
Project status
Not recorded
Tariff structure
Capacity + Energy
Capacity charge
Not stated
Energy charge
Not stated
Key risk features
Take-or-pay Currency indexation Change-in-law protection Termination compensation
Indexation formula
Capital-recovery-and-tax component fixed for the Term. Fixed O&M and Variable O&M components escalate annually by a US price index (labelled 'Producer Price Index' in the PPA but citing the US Consumer Price Index series). Fuel price component adjusts quarterly under the Fuel Supply Agreement(s) and PURC's Automatic Adjustment Formula. Tariff is invoiced in USD and paid in Ghana Cedis using a Buyer-funded Hedged Exchange Rate.
Project overview
Installed capacity (MW)
378 (at ISO Conditions), described as Contracted Capacity; two Frame 9E gas turbines plus one 130 MW steam turbine Source: 'Contracted Capacity' definition; Sch. 2 Part A (p. 7; 60)
Expected annual generation
Not in contract
Commercial operation date (COD)
36 months after the Effective Date (Scheduled COD), or such later date as the Parties agree; Long Stop COD is 6 months after the Scheduled COD. The Effective Date itself is targeted within 12 months of the Signature Date (Scheduled Effective Date), with an 18-month Long Stop Effective Date. Source: 'Scheduled Commercial Operation Date', 'Long Stop Commercial Operation Date', 'Scheduled Effective Date', 'Long Stop Effective Date' definitions; Sch. 14 (p. 13; 11; 80)
PPA expiry
20 years from the Commercial Operation Date, unless earlier terminated or extended; the formal 'Term' itself begins running from the (earlier) Effective Date. After COD the Term is extended day for day for delay caused by Force Majeure, a Buyer breach or an ETU breach of the Connection Agreement (cl. 16.6(b)). Source: 'Term' definition; Sch. 14; cl. 16.6(b) (p. 14; 80; 32)
Contract term (years)
20 (from COD; total nominal Term is longer, see PPA Expiry Date row) Source: 'Term' definition (p. 14)
Contracting parties
Transmission service provider
Ghana Grid Company Limited (GRIDCo), referred to in the PPA as 'ETU' Source: 'ETU' definition (p. 8)
Government support entity
Not addressed in the PPA; may be addressed in related documents.
Project sponsors / shareholders
Not stated in the PPA
Ultimate beneficial owner(s)
Not in contract
Commercial terms
Contract type
Capacity and Energy PPA Source: cl. 8.1-8.2 (p. 20)
Contracted capacity (MW)
378 (ISO Conditions) Source: 'Contracted Capacity' definition (p. 7)
Tariff currency
US Dollars (invoiced and calculated); payable in Ghana Cedis at the agreed Hedged Exchange Rate Source: cl. 8.2; 11.5(d) (p. 20; 26)
Indexation: inflation
Yes Source: cl. 8.3(b)-(c) (p. 21-23)
Indexation: foreign exchange
Yes Source: cl. 11.5 (p. 26-27)
Indexation: fuel price
Yes Source: cl. 8.3(c); Sch. 15 s.3.0 (p. 22-23; 84)
Indexation: none / fixed tariff
No
Indexation: other
No
Summary of indexation methodology
Capital-recovery-and-tax component (CRTC) fixed for the Term. Fixed O&M and Variable O&M components are escalated annually by a US Bureau of Labor Statistics price index (the PPA calls it the Producer Price Index but cites series CUUR0000SA0, which is the US Consumer Price Index; PURC's approval letter calls it CPI). Fuel price component adjusts quarterly under the Fuel Supply Agreement(s) and PURC's Automatic Adjustment Formula (which also tracks the GHS/USD exchange rate and fuel mix). Tariff is invoiced in USD and paid in Ghana Cedis using a Buyer-funded Hedged Exchange Rate. Source: cl. 8.3(b)-(c); 11.5; Sch. 15 s.3.0-4.0 (p. 21-23; 23-24; 84-85)
Billing and payment cycle
Monthly. Seller invoices within 10 days after each month-end; Due Date is 45 days after the Buyer receives the Invoice. Disputes require an Invoice Dispute Notice before the Due Date (undisputed portion still due); unresolved disputes after 14 days go to Expert Determination. Billing errors are corrected/refunded within 21 days. Total Electricity Charge invoiced in USD but paid in GHS at the agreed Hedged Exchange Rate; local costs billed and paid directly in Cedis. Late payment (30+ days overdue) accrues Default Interest = LIBOR + 0.05 percentage points per annum. The Buyer must fund and maintain a bank payment guarantee ('the Account', cl. 12) equal to 2 months of invoicing, which the Seller can draw on if unpaid 30 days after the Due Date; if still unpaid, the Seller may suspend Capacity/Energy delivery. Source: cl. 11.1-11.5; 12; 14.5; 'Due Date', 'Default Interest Rate' definitions (p. 7; 25-28; 29)
Government and consumer exposure
Take-or-pay details
The Capacity Charge is paid on the Capacity the Seller makes Available (ACAPbp in the formula), not on the Energy actually dispatched or taken by the Buyer - so the Buyer pays a capacity charge even in months when it does not call for energy from the plant. Grid Events also result in 'Deemed Available Capacity', for which the Capacity Charge continues to be paid. The Energy Charge, by contrast, is only paid on Energy actually delivered. Cl. 14.4 adds that any interruption or restriction of the Seller's supply does not relieve the Buyer of its obligation to pay the Total Electricity Charge. Source: cl. 7.4; 8.2-8.3(b); 14.4 (p. 19-21; 29)
Minimum offtake requirement
No
Government guarantee
No
Letter of support
No
Foreign exchange protection mechanism
Yes Source: cl. 8.4; 11.5 (p. 23; 26-27)
Foreign exchange protection details
The Seller must maintain a Quarterly Exchange Rate Hedge Agreement with a reputable Ghana commercial bank (best available rate), and provide copies to the Buyer and PURC; the Buyer pays all costs of the hedge. The Total Electricity Charge is invoiced in USD and paid in GHS at the agreed Hedged Exchange Rate. If the Seller cannot renew the hedge despite diligent efforts (with the Buyer's cooperation), the prevailing PURC exchange rate is used instead, and any gap between the PURC rate and the actual market rate is added to the following Billing Period's price. Source: cl. 11.5; 8.4 (p. 26-27; 23)
Fiscal incentives and non-tariff government support
None found. No tax holiday, duty/VAT/NHIL exemption, or stabilization clause. Invoices expressly apply 'any required Taxes applicable at the time of invoicing' (cl. 11.1(e)), and the pro-forma invoice (Sch. 1) lists VAT and NHIL as payable line items. Corporate tax cost is instead priced into the tariff itself: the Capacity Charge's CRTC component recovers 'corporate taxes payable by the Seller', and PURC's approved tariff (Sch. 15) includes an explicit Tax Recovery Charge of 0.5458 UScents/kWh. Source: cl. 11.1(e); 8.3(b); Sch. 1; Sch. 15 Table 1/3 (p. 25; 21; 49-51; 83-85)
Risk allocation
Fuel supply risk borne by
Shared Source: cl. 5.5(f); 8.3(c)-(d) (p. 17; 21-23)
Resource availability risk borne by
Not applicable
Foreign exchange risk borne by
Offtaker Source: cl. 11.5(c) (p. 26)
Change in law risk borne by
Offtaker Source: cl. 9; 10 (p. 24; 24-25)
Transmission and grid availability risk borne by
Offtaker Source: cl. 7.4; 'Grid Event' definition (p. 19-20; 9)
Summary of key risk allocation provisions
Fuel: shared. Seller must hold Fuel Supply Agreements and chooses the fuel mix (security of supply is the Seller's risk), but the fuel price itself passes through in the Energy Charge on a quarterly-adjusted, pass-through basis (Buyer's risk). Change in Law and Grid Event risk both land on the Buyer/tariff: Increased Costs from a Change in Law can be charged to the Buyer (subject to PURC approval and a materiality threshold), and a Grid Event keeps the Capacity Charge flowing to the Seller as 'Deemed Available Capacity' even with no energy delivered. FX conversion cost is the Buyer's, which funds the Exchange Rate Hedge Arrangements. Resource availability risk is not applicable (thermal). Government support is not addressed at all in the PPA - unlike the AKSA pilot contract, there is no clause excluding or providing for it, so related documents (if any) should be checked. Source: cl. 5.5(f); 7.4; 8.3(c)-(d); 9; 10; 11.5 (p. 17; 19-20; 21-24; 24-25; 26-27)
Performance obligations
Performance guarantee
No Source: 'Commissioning Certificate' definition; Sch. 7 (p. 6; 69-71)
Summary of performance obligations
The Commissioning Certificate requires tested Capacity of at least 95% of the 378 MW Contracted Capacity. Ongoing Capacity Tests (Schedule 7) may be called by either Party, corrected to stated Guarantee Conditions (30 degC, 1012 mbar, 60% relative humidity, 0.8 power factor lagging, 161/330 kV, 50Hz); if a test shows Seller overstated Available Capacity, the tested (lower) figure is used going forward and the Seller pays the test cost; if understated, the Buyer pays the test cost. No ongoing availability percentage or numeric heat-rate guarantee is stated (Schedule 2 Part B is blank - see Availability Requirement row). Source: 'Commissioning Certificate' definition; cl. 7.3; Sch. 7 (p. 6; 19-20; 69-71)
Curtailment compensation
Applicable Source: cl. 7.4 (p. 19-20)
Summary of curtailment arrangements
If a Grid Event (grid/interconnection failure attributable to the Power Evacuation System, ETU or an Emergency) prevents the Seller from delivering Energy after a Dispatch Instruction, the Facility is deemed Available and the Buyer continues to pay the Capacity Charge on that Deemed Available Capacity. No equivalent relief was found for the Energy Charge component (no energy delivered means no Energy Charge is payable). Cl. 14.4 states that interruptions or restrictions of the Seller's supply do not relieve the Buyer of its payment obligation; cl. 14.3 lets the Seller discontinue supply during a Buyer default, Political Event or Grid Event. Source: cl. 7.4; 14.3-14.4; 'Grid Event' definition (p. 19-20; 29; 9)
Force majeure, default and termination
Force majeure provisions
Force Majeure is any circumstance beyond the Affected Party's reasonable control meeting a 5-part test (unavoidable, prevents performance except payment, all reasonable precautions taken, not caused by the Affected Party's own breach, without its fault), and 'shall include' war, acts of God and epidemics if they meet that test. Notice within 7 days, with ongoing mitigation and progress reports. The Buyer cannot claim Force Majeure for its payment obligations. The Seller is paid for Energy actually delivered during a Force Majeure event affecting it, but the PPA does not say whether the Capacity Charge continues if Force Majeure prevents the Seller from making Capacity available at all - a gap worth flagging. If Force Majeure continues for more than 12 months (plus a 6-month cooling-off period), either Party may terminate (cl. 21.4); cl. 16.5(d) says the terms of such a termination are to be agreed by the Parties. Scheduled Effective Date/COD are pushed back day-for-day for delay caused by Force Majeure or a counterparty breach. Source: cl. 16.1-16.6; 21.4 (p. 30-32; 42)
Termination compensation: seller default
Not stated Source: cl. 21.2 (p. 40-41)
Termination compensation: buyer default
Fair Market Value Source: cl. 21.3; Sch. 13 (p. 41-42; 79)
Termination compensation: political force majeure
Fair Market Value Source: cl. 21.5; Sch. 13 (p. 42; 79)
Summary of termination compensation framework
On (i) Buyer default and (ii) Political Event / Change-in-Law termination, the Buyer pays the Seller a negotiated 'Seller Termination Payment' expressly pegged to 'the prevailing market value of the Facility' (no valuation method, cap or timetable is stated; the figure is to be negotiated), and the Facility is transferred to the Buyer under Schedule 13 (Transfer Procedures) once payment clears. No compensation is specified where the Buyer terminates for Seller default (cl. 21.2) or where the Agreement ends through ordinary (non-Political) Force Majeure (cl. 21.4) - both are silent on payment. The general liability cap (US$5,000,000 in any Year, US$30,000,000 aggregate, rising to US$30,000,000 in the final Year before a Transfer) expressly does not apply to termination payments. For non-political Force Majeure, cl. 16.5(d) says the terms of any termination are to be agreed by the Parties; cl. 19.2 refers to a transfer of the Facility on Seller-default or Force Majeure termination, but cl. 21.2 and 21.4 contain no transfer or payment mechanism. Source: cl. 16.5(d); 19.2; 21.2-21.5; Sch. 13 (p. 32; 36; 40-42; 79)
Dispute resolution
Governing law
Laws of Ghana Source: cl. 24 (p. 44)
Dispute resolution: negotiation / mediation
Yes Source: cl. 25.1 (p. 44)
Dispute resolution: expert determination
Yes Source: cl. 25.2 (p. 44-45)
Dispute resolution: arbitration
Yes Source: cl. 25.3 (p. 46)
Dispute resolution: court proceedings
No Source: cl. 25.3(h), (j) (p. 46)
Dispute resolution: other
No
Arbitration seat
Accra, Ghana Source: cl. 25.3(f) (p. 46)
Applicable arbitration rules
Alternative Dispute Resolution Act, 2010 (Act 798) of Ghana (defined in the PPA as the 'Arbitration Rules'); 3 arbitrators; English language Source: cl. 25.3(a)-(g) (p. 46)
Amendments
Number of amendments executed
Not in contract (base PPA only; no amendments in the set provided) Source: cl. 29 (p. 50)