GH-PPA-DRAFT-03
BXC 20 MW Solar Project, Gomoa Onyadze
BXC Company (Ghana) Limited · Solar PV · 20.00 MW · Gomoa Onyadze, Gomoa East, Central Region, Ghana
GH-PPA-DRAFT-03
BXC 20 MW Solar Project, Gomoa Onyadze
BXC Company (Ghana) Limited · Solar PV · 20.00 MW · Gomoa Onyadze, Gomoa East, Central Region, Ghana
Summary
A 20 MW solar PV plant in Gomoa Onyadze (expandable to 80 MW at the developer's option), supplying ECG under a 20-year energy-only PPA signed 17 June 2013 (extendable by 5 years). A flat PURC feed-in tariff of 20.1372 US cents/kWh applies for the first 10 years, renegotiated within a PURC range thereafter, with a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2013-06-17
- Financial close
- —
- Commercial operation
- —
- Contract end
- —
- Contract duration
- 20 years
- Contract status
- Active
- Tariff structure
- Energy-only
- Capacity charge
- —
- Energy charge
- USD 20.1372/kWh
- Key risk features
- Take-or-pay Currency indexation
- Indexation formula
- Fixed USD rate for years 1-10, paid in Ghana cedis at the PURC-approved exchange rate; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 10 years of the 20-year term.