GH-PPA-DRAFT-03

BXC 20 MW Solar Project, Gomoa Onyadze

BXC Company (Ghana) Limited · Solar PV · 20.00 MW · Gomoa Onyadze, Gomoa East, Central Region, Ghana

Summary

A 20 MW solar PV plant in Gomoa Onyadze (expandable to 80 MW at the developer's option), supplying ECG under a 20-year energy-only PPA signed 17 June 2013 (extendable by 5 years). A flat PURC feed-in tariff of 20.1372 US cents/kWh applies for the first 10 years, renegotiated within a PURC range thereafter, with a take-or-pay obligation.

Key terms

Offtaker
Electricity Company of Ghana (ECG)
Signing date
2013-06-17
Financial close
—
Commercial operation
—
Contract end
—
Contract duration
20 years
Contract status
Active
Tariff structure
Energy-only
Capacity charge
—
Energy charge
USD 20.1372/kWh
Key risk features
Take-or-pay Currency indexation
Indexation formula
Fixed USD rate for years 1-10, paid in Ghana cedis at the PURC-approved exchange rate; year-11 reset negotiated within a PURC range with a floor at the original rate, applying for the remaining 10 years of the 20-year term.