GH-PPA-02
Astro Power 220 MW Combined-Cycle Power Plant, Aboadze
Astro Power Limited · Thermal (Gas) · 220.00 MW · Near Aboadze, Ghana
GH-PPA-02
Astro Power 220 MW Combined-Cycle Power Plant, Aboadze
Astro Power Limited · Thermal (Gas) · 220.00 MW · Near Aboadze, Ghana
Summary
A 220 MW (nominal) dual-fuel (gas/liquid) combined-cycle plant near Aboadze, supplying ECG under a 20-year capacity-and-energy PPA signed 13 October 2014 (extendable by 5 years). The tariff combines fixed and variable capacity charges with a heat-rate-based energy charge tied to gas or light crude oil pricing, and a take-or-pay obligation. Change-in-law risk is borne by ECG.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2014-10-13
- Financial close
- Not stated
- Commercial operation
- Combined Cycle mode COD: the day after issuance of the Commissioning Test Report (cl. 6.3). Scheduled Commercial Operation Date is 15.5 months after the Effective Date. Source: cl. 6.3; 'Scheduled Commercial Operation Date' definition (p. 17; 12)
- Contract end
- 20 years from the Commercial Operation Date (the 'End Date'); the Buyer must extend for a further 5 years at the Seller's request if the Seller shows in the last 12 months of the term that the plant remains commercially competitive Source: cl. 4; 'End Date' definition (p. 15; 9)
- Contract duration
- 20 years
- Contract status
- Active
- Project status
- Not recorded
- Tariff structure
- Capacity + Energy
- Capacity charge
- Unit Capacity Charge = Unit Fixed Capacity Charge (0.0375 US$/kWh, investment cost recovery) + Unit Variable Capacity Charge (0.0079 US$/kWh, fixed O&M recovery). Both are multiplied by (actual energy generated + Deemed Energy) as part of the TEC formula; there is no separate per-MW-month capacity fee. Source: cl. 7.1-7.2 (p. 18-19)
- Energy charge
- Unit Energy Charge = contracted Heat Rate x gas price (US$/MMBTU, fixed quarterly under the Gas Supply Agreement and passed through via PURC); for light crude oil or blended operation, a weighted formula applies (%gas x Heat Rate(gas) x Gas Price + %LCO x Heat Rate(LCO) x LCO Price). Source: cl. 7.2(b); 7.3 (p. 19)
- Key risk features
- Take-or-pay Currency indexation Change-in-law protection
- Indexation formula
- No inflation index found for the capacity components. Gas price is fixed quarterly under the Gas Supply Agreement and passed through the tariff by PURC. The USD tariff is paid in cedis using a quarterly Exchange Rate Hedge Agreement, with the cost of the hedge also reimbursed to the Seller.
Project overview
- Expected annual generation
- 1,757,606 MWh (the contracted Annual Energy) Source: cl. 3.1; 3.4 (p. 14)
- Commercial operation date (COD)
- Combined Cycle mode COD: the day after issuance of the Commissioning Test Report (cl. 6.3). Scheduled Commercial Operation Date is 15.5 months after the Effective Date. Source: cl. 6.3; 'Scheduled Commercial Operation Date' definition (p. 17; 12)
- PPA expiry
- 20 years from the Commercial Operation Date (the 'End Date'); the Buyer must extend for a further 5 years at the Seller's request if the Seller shows in the last 12 months of the term that the plant remains commercially competitive Source: cl. 4; 'End Date' definition (p. 15; 9)
- Contract term (years)
- 20 (Seller may require a 5-year extension if the plant remains commercially competitive) Source: cl. 4 (p. 15)
Contracting parties
- Transmission service provider
- Ghana Grid Company (GRIDCo) Source: 'GRIDCo', 'Connection Agreement', 'NITS' definitions (p. 11; 9)
- Government support entity
- Not addressed in the PPA itself. A separate 'Government Consent and Support Agreement' between the Seller and the Government is defined and is a condition precedent to the Seller's obligations (cl. 5.1(b)), but its terms are not part of this document. Cl. 13.4 implies that this Government Consent is expected to pay overdue invoices if the Buyer's Bank Guarantee does not. Source: cl. 5.1(b); 'Government Consent and Support Agreement' definition; 13.4 (p. 15; 10; 25)
- Project sponsors / shareholders
- Not in contract
- Ultimate beneficial owner(s)
- Not in contract
Commercial terms
- Contract type
- Capacity and Energy PPA Source: cl. 7.1-7.2 (p. 18)
- Contracted capacity (MW)
- 220 nominal (phased: 150 MW at Trial Operations, up to 220 MW at COD, per Schedule 6) Source: Recitals; Sch. 6 (p. 6; 46)
- Tariff currency
- US Dollars, invoiced in USD and payable in Ghana cedis at an agreed Hedged Exchange Rate Source: cl. 7.5; 10.4(b) (p. 20; 23)
- Capacity charge
- Unit Capacity Charge = Unit Fixed Capacity Charge (0.0375 US$/kWh, investment cost recovery) + Unit Variable Capacity Charge (0.0079 US$/kWh, fixed O&M recovery). Both are multiplied by (actual energy generated + Deemed Energy) as part of the TEC formula; there is no separate per-MW-month capacity fee. Source: cl. 7.1-7.2 (p. 18-19)
- Energy charge
- Unit Energy Charge = contracted Heat Rate x gas price (US$/MMBTU, fixed quarterly under the Gas Supply Agreement and passed through via PURC); for light crude oil or blended operation, a weighted formula applies (%gas x Heat Rate(gas) x Gas Price + %LCO x Heat Rate(LCO) x LCO Price). Source: cl. 7.2(b); 7.3 (p. 19)
- Tariff escalation mechanism
- The Unit Fixed and Unit Variable Capacity Charges are not stated to escalate (no CPI or other index found in the text). The gas price component (GP) is fixed quarterly through the Gas Supply Agreement and passed through the tariff via PURC; light crude oil pricing is negotiated case by case. The agreed FX hedge rate, and the cost of the hedge, are also built into the amount actually invoiced. Source: cl. 7.2(b)(iii); 7.4-7.5 (p. 19; 20)
- Indexation: inflation
- No
- Indexation: foreign exchange
- Yes Source: cl. 7.4-7.5; 10.4 (p. 20; 23)
- Indexation: fuel price
- Yes Source: cl. 7.2(b)(iii) (p. 19)
- Indexation: none / fixed tariff
- No
- Indexation: other
- No
- Summary of indexation methodology
- No inflation index found for the capacity components. Gas price is fixed quarterly under the Gas Supply Agreement and passed through the tariff by PURC. The USD tariff is paid in cedis using a quarterly Exchange Rate Hedge Agreement, with the cost of the hedge also reimbursed to the Seller. Source: cl. 7.2(b)(iii); 7.4-7.5 (p. 17-18)
- Billing and payment cycle
- Monthly. Invoice submitted by the 10th day of the following month; Due Date is 45 days after the Buyer receives the Invoice; VAT applied on invoicing. Invoice Dispute Notice must be given before the Due Date (undisputed portion still payable); if none is given, the Buyer may still dispute within 1 year. Interest at the Default Rate (0.1 percentage point above LIBOR) accrues on amounts overdue more than 30 days. From COD ECG must maintain a USD 25 million Bank Guarantee that the Seller may draw on for amounts overdue 30 days (cl. 11); if an Invoice is unpaid 30 days after the Due Date and neither the Bank Guarantee nor the Government Consent pays it, the Seller may discontinue supply (cl. 13.4). Source: cl. 10.1-10.4; 'Due Date', 'Default Rate' definitions; 11; 13.4 (p. 22-24; 9; 24-25)
Government and consumer exposure
- Take-or-pay obligation
- Yes Source: cl. 7.1; 7.8 (p. 18; 20)
- Take-or-pay details
- If the actual annual Energy delivered is below the contracted minimum Annual Energy of 1,702,103 MWh for reasons attributable to the Buyer, the Buyer pays the Seller the shortfall as if it had been produced. Deemed Energy (assessed at 92% availability) is also payable for NITS- or Buyer-caused shortfalls. Source: cl. 7.8(b); 'Deemed Energy' definition (p. 20-21; 9)
- Minimum offtake requirement
- Yes Source: cl. 7.8 (p. 20-21)
- Minimum offtake details
- Annual Energy target is 1,757,606 MWh, with a contracted minimum of 1,702,103 MWh. The annual true-up applies from the second anniversary of COD; the first 12 months are exempt (cl. 3.4(b)). If actual annual delivery falls short of the minimum for reasons attributable to the Seller, the Seller compensates the Buyer at the System Marginal Price differential; if attributable to the Buyer, the Buyer pays the Seller as if the energy had been produced. A discount applies to the Buyer for delivery above 1,813,110 MWh. Source: cl. 3.4(b); 7.8-7.9 (p. 15; 20-21)
- Government guarantee
- Not stated Source: cl. 5.1(b); 'Government Consent and Support Agreement' definition (p. 15; 10)
- Letter of support
- Not stated
- Foreign exchange protection mechanism
- Yes Source: cl. 7.4-7.5; 10.4 (p. 20; 23)
- Foreign exchange protection details
- Each Quarter the Seller must enter a GHS/USD Exchange Rate Hedge Agreement with a Ghanaian commercial bank; the USD tariff is invoiced monthly and paid in cedis at that hedged rate, and the cost of the hedge itself is also paid to the Seller. The rate is communicated to PURC. Source: cl. 7.4-7.5 (p. 20)
- Fiscal incentives and non-tariff government support
- No statutory tax exemption, duty/VAT exemption, or stabilization clause found in the PPA. To the contrary, the Invoice is expressly required to include applicable VAT (cl. 10.1(c)), and the pro-forma invoice (Schedule 1) itemises both VAT and NHIL. All payments are made free of set-off or withholding, but with no exemption from Taxes generally (cl. 10.4(d)). Source: cl. 10.1(c); 10.4(d); Sch. 1 (p. 22-23; 40)
Risk allocation
- Fuel supply risk borne by
- Shared Source: cl. 7.1; 7.2(b)(iii); 'Fuel Oil Supply Agreement', 'Gas Supply Agreement' definitions (p. 18-19; 10)
- Resource availability risk borne by
- Not applicable
- Foreign exchange risk borne by
- Offtaker Source: cl. 7.4-7.5; 10.4 (p. 20; 23)
- Change in law risk borne by
- Offtaker Source: cl. 8.1-8.3; 'Political Event' definition (p. 21-22; 12)
- Transmission and grid availability risk borne by
- Offtaker Source: 'Deemed Energy' definition; cl. 7.1 (p. 9; 18)
- Summary of key risk allocation provisions
- Fuel: shared. The Seller procures and is responsible for gas/light-crude-oil supply, but the gas price passes through the Energy Charge and any take-or-pay payments the Seller owes under its natural gas/LNG supply arrangements (not fuel oil) are reimbursed to it as Fuel Reconciliation. FX risk sits with the Buyer, which must fund a quarterly hedge and reimburse the hedge cost. Change in Law/Political Event costs are recoverable by the Seller through a PURC-approved tariff adjustment (Increased Costs), so this risk ultimately falls on the Buyer/consumers, subject to regulatory process. Grid/NITS-caused and Buyer-caused shortfalls are compensated as Deemed Energy, so grid risk sits with the Buyer. ECG must post a USD 25 million Bank Guarantee as payment security (cl. 11). No government guarantee or letter of support is stated in the PPA itself; a separate Government Consent and Support Agreement is a condition precedent and cl. 13.4 implies it may backstop overdue payments. Source: cl. 5.1(b); 7; 8; 'Deemed Energy'
Performance obligations
- Availability requirement
- No fixed availability percentage guarantee is stated for the Seller. Deemed Energy for NITS/Buyer-caused shortfalls is calculated assuming 92% availability. If the Seller has paid annual-shortfall compensation under cl. 7.8(a) for at least 6 months in any 12-month period, the Buyer may issue a warning notice; if the shortfall is not remedied within a further 3 months, the Seller is in default if the Facility then fails to supply at least 814 GWh over the following 183 continuous days (credited for NITS/Buyer/Force-Majeure/maintenance/Emergency/temperature-derating volumes). Source: 'Deemed Energy' definition; cl. 20.1 (p. 9; 32-33)
- Performance guarantee
- Yes Source: cl. 7.8(a); 6.4-6.5 (p. 20; 17-18)
- Curtailment compensation
- Applicable Source: 'Deemed Energy' definition; cl. 7.1 (p. 9; 18)
- Summary of curtailment arrangements
- NITS- or Buyer-caused shortfalls are paid as Deemed Energy (at 92% assumed availability) as though delivered. The plant is contracted as a Base-Load Plant subject to GRIDCo merit-order dispatch (cl. 7.7). The Seller may discontinue supply for safety, on GRIDCo instruction, for Seller Force Majeure, or on 72 hours' notice for emergency maintenance (cl. 13.3). The PPA does not separately address a Buyer-initiated economic curtailment right or its compensation. Source: 'Deemed Energy' definition; cl. 7.7; 13.3 (p. 9; 20; 25)
Force majeure, default and termination
- Force majeure provisions
- Broad Force Majeure definition (war, armed conflict, act of God, epidemic, etc., after the Signature Date) requiring the event to be unavoidable, unforeseeable-in-effect and without the Affected Party's fault. The Affected Party must notify within 7 days and mitigate. During Seller Force Majeure after COD, the Buyer must still pay for Energy delivered; the Buyer cannot claim Force Majeure for its own payment obligations. No Force-Majeure-triggered termination right or termination payment is stated anywhere in the PPA. Source: cl. 14.1-14.5 (p. 26-28)
- Termination rights
- Buyer may terminate for uncured Seller default (warning notice once the Seller has paid cl. 7.8(a) shortfall compensation for 6 months in a 12-month period, 3-month remedy period, then the 814 GWh/183-day threshold under cl. 20.1). Seller may terminate for uncured Buyer payment default (30 days). Either party may terminate for the other's insolvency/liquidation or a merger/asset transfer to a non-committing successor (cl. 21.4). Either party may also terminate if Conditions Precedent are not satisfied or waived within 12 months of the Signature Date (subject to a diligence proviso protecting the Seller). Source: cl. 5.3; 20.1-20.2; 21.1-21.4 (p. 15-16; 32-34)
- Termination compensation: seller default
- Not stated Source: cl. 21.2(b); 19.3 (p. 33-34; 32)
- Termination compensation: buyer default
- Not stated Source: cl. 21.3; 19.3; 20.4 (p. 34; 32)
- Termination compensation: political force majeure
- Not stated
- Summary of termination compensation framework
- No termination-payment formula is stated for any scenario. On Seller default, the Buyer's payment obligation for energy already supplied is reduced by the Seller's liabilities to the Buyer; on Buyer default, the Seller may claim compensation for losses (cl. 19.3/20.4). The only quantified payment on default/delay is the late-COD liquidated damages under cl. 6.4 (US$10,000/day, capped at US$1 million, secured by the Performance Bond) which is a completion guarantee, not a termination fee. Each Party's total liability under the Agreement (outside cl. 3.4, 6.4, 7, 8, 9 and 19.2) is capped at US$2 million. Source: cl. 6.4; 19.3; 20.4; 21.2-21.3 (p. 17-18; 32; 33-34)
Dispute resolution
- Governing law
- Laws of Ghana Source: cl. 23 (p. 34)
- Dispute resolution: negotiation / mediation
- Yes Source: cl. 24.1 (p. 34-35)
- Dispute resolution: arbitration
- Yes Source: cl. 24.2 (p. 35)
- Dispute resolution: court proceedings
- No
- Dispute resolution: other
- No
- Arbitration seat
- London, England Source: cl. 24.2(b) (p. 35)
- Applicable arbitration rules
- ICC Rules of Arbitration; 3 arbitrators; English language Source: cl. 24.2(a)-(c) (p. 35)
Amendments
- Number of amendments executed
- Not in contract (base PPA only; no amendments in the set provided) Source: cl. 27.1 (p. 36)