GH-PPA-01
AKSA Takoradi 900 MW Combined Cycle Power Plant
AKSA Energy Company Ghana Limited · Thermal (Gas) · 900.00 MW · Takoradi, Ghana
GH-PPA-01
AKSA Takoradi 900 MW Combined Cycle Power Plant
AKSA Energy Company Ghana Limited · Thermal (Gas) · 900.00 MW · Takoradi, Ghana
Summary
A 900 MW (ISO) two-phase natural gas combined-cycle plant in Takoradi, supplying ECG under a 20-year capacity-and-energy PPA signed 8 November 2024. The tariff blends a fixed capacity charge with a gas-indexed energy charge (US CPI and PURC weighted average gas cost), with a take-or-pay obligation and FX pass-through. Change-in-law risk is borne by ECG.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2024-11-08
- Financial close
- Not stated
- Commercial operation
- Not stated
- Contract end
- Not stated
- Contract duration
- 20 years
- Contract status
- Active
- Project status
- Not recorded
- Tariff structure
- Capacity + Energy
- Capacity charge
- Not stated
- Energy charge
- Not stated
- Key risk features
- Take-or-pay Currency indexation Change-in-law protection Termination compensation
- Indexation formula
- US CPI-U annual escalation on O&M components; fuel component tracks PURC's weighted average cost of gas; USD tariff paid in cedis with an FX adjustment reconciling AKSA's actual conversion gains or losses (incl. hedging costs).
Project overview
- Expected annual generation
- Not in contract
- Contract term (years)
- 20 Source: 'PPA PDS Term' definition; cl. 5.6(a) (p. 10; 23)
Contracting parties
- Transmission service provider
- Ghana Grid Company (GRIDCo) as ETU Source: 'ETU' and 'GRIDCo' definitions (p. 7; 9)
- Government support entity
- The PPA states that no Government financial support or backstop will be provided under it (cl. 2.7); Ministry of Energy no-objection is a condition precedent. Related documents may address support separately. Source: cl. 2.7; Annex 7A (p. 15; 57)
- Project sponsors / shareholders
- Affiliate of AKSA Enerji Uretim A.S. (Turkey) Source: cl. 11; 'AKSA Turkey' definition; Annex 2 (p. 25; 6; 49)
- Ultimate beneficial owner(s)
- Not in contract
Commercial terms
- Contract type
- Capacity and Energy PPA Source: cl. 5.1 (p. 18-19)
- Contracted capacity (MW)
- 750 (+/-10%) net Guaranteed Capacity Source: cl. 2.3(b) (p. 14)
- Tariff currency
- US Dollars, payable in Ghana cedis at the effective exchange rate with an FX true-up Source: Annex 6 paras 1-3, 6 (p. 55)
- Tariff structure summary
- Monthly PDS Fee = Monthly Fixed O&M Charge + Monthly Utilization Charge. Total 10.1948 US cents/kWh at signing-date gas price and full load: Capital Recovery 3.7350 + Fixed O&M 0.7122 + Non-Fuel Variable O&M 0.4578 + Fuel Recovery 5.2898 (at WACoG of US$7.8368/MMBtu). Source: cl. 5.1(a) (p. 18-19)
- Tariff escalation mechanism
- Capital Recovery Charge fixed for the term. Fixed O&M and Non-Fuel Variable O&M escalate annually with US CPI-U from the Signing Date. Fuel Recovery Charge follows PURC's WACoG. Source: cl. 5.1(c)-(d) (p. 19)
- Indexation: inflation
- Yes Source: cl. 5.1(c) (p. 19)
- Indexation: foreign exchange
- Yes Source: Annex 6 paras 2-9 (p. 55-56)
- Indexation: fuel price
- Yes Source: cl. 5.1(d) (p. 19)
- Indexation: none / fixed tariff
- No
- Indexation: other
- No
- Summary of indexation methodology
- US CPI-U annual escalation on O&M components; fuel component tracks PURC's weighted average cost of gas; USD tariff paid in cedis with an FX adjustment reconciling AKSA's actual conversion gains or losses (incl. hedging costs). Source: cl. 5.1(c)-(d); Annex 6 (p. 19; 55-56)
Government and consumer exposure
- Take-or-pay obligation
- Yes Source: cl. 5.1(b); 5.7 (p. 19; 23)
- Take-or-pay details
- Fixed O&M paid on full Guaranteed Capacity regardless of dispatch; Capital Recovery Charge paid on deemed energy up to the 60% Guaranteed Dispatch; charges continue during AKSA suspensions for non-payment. Source: cl. 5.1(b); 5.7; 21.4 (p. 19; 23; 34)
- Minimum offtake requirement
- Yes Source: cl. 5.7 (p. 23)
- Minimum offtake details
- ECG must dispatch at least 60% of Guaranteed Capacity per year; shortfall invoiced monthly as deemed energy. ECG is the sole and exclusive customer, but export sales count toward the 60%. Source: cl. 5.7; 2.6 (p. 23)
- Government guarantee
- No Source: cl. 2.7 (p. 15)
- Letter of support
- No Source: cl. 2.7 (p. 15)
- Foreign exchange protection mechanism
- Yes Source: Annex 6 (p. 55-56)
- Foreign exchange protection details
- Invoices in USD, paid in cedis; each invoice reconciled so AKSA is compensated for conversion losses (incl. hedging costs). Parties to negotiate a hedging arrangement in good faith. Source: Annex 6 paras 5-10 (p. 55)
- Other government commitments
- Ministry of Energy no-objection and PURC approval are conditions precedent. ECG covenants to pay Nationalisation Damages and not to encourage expropriation; ECG (through the Ministry) to handle import/export duties on spares. ECG waives sovereign immunity over its assets and revenues and covenants no restrictions on payments; termination fee payable in USD offshore. Source: Annex 7A; cl. 12.1; 4(l); 27; 5.6(b) (p. 57; 26; 18; 40; 23)
- Fiscal incentives and non-tariff government support
- The PPA anticipates (but does not itself grant) a statutory tax exemption and tax-free temporary import, subject to approvals. If the exemption is not obtained, ECG reimburses import taxes and duties (invoiced in year 1 after COD). Fees are paid net of all Ghana taxes except corporate income tax, and ECG reimburses any other new taxes incl. their financing cost. Gas interconnection costs within WACoG pass to ECG. Source: cl. 16.1-16.4; 4(m); 5.5(c)(v); 3.1(f) (p. 31; 18; 22; 15)
Risk allocation
- Fuel supply risk borne by
- Shared Source: cl. 7.1-7.3; 5.1(d); 5.5(c)(vii) (p. 23-24; 19; 22)
- Resource availability risk borne by
- Not applicable
- Foreign exchange risk borne by
- Offtaker Source: Annex 6 (p. 55-56)
- Change in law risk borne by
- Offtaker Source: cl. 15 (p. 30)
- Transmission and grid availability risk borne by
- Offtaker Source: 'Excusable Event' definition; cl. 2.5 (p. 7; 14-15)
- Summary of key risk allocation provisions
- Fuel: shared. AKSA procures gas at its own cost and bears all supply and delivery risk ('Fuel Supply Failure' gives no relief); ECG bears gas price risk through the WACoG pass-through and the knock-on of its own payment defaults. ECG also carries dispatch, FX, change in law and grid risk: capacity charges are paid on Guaranteed Capacity, grid failures count as deemed availability, and costs of new law are indemnified. AKSA carries heat-rate and availability risk. Cl. 2.7 excludes Government support under this PPA; related agreements should be checked. Source: cl. 2.5; 2.7; 5.1; 5.2; 5.5(c)(vii); 7; 15; Annex 6
Performance obligations
- Availability requirement
- Guaranteed Annual Availability of 92% of Guaranteed Capacity. AKSA default if average available + deemed capacity is below 60% of Guaranteed Capacity over any rolling 365 days, where the shortfall is attributable to AKSA. Source: cl. 2.3(g); 22.3(c) (p. 14; 35)
- Performance guarantee
- Yes Source: cl. 5.2; Annex 8 (p. 19-20; 59-60)
- Summary of performance obligations
- Contracted heat rate 6,750 Btu/kWh: AKSA pays excess fuel cost; savings shared 50:50. Capacity verified by annual and up to 5 ECG-requested tests; overstated capacity is credited back. No availability liquidated damages found beyond capacity-based payment. Source: cl. 5.2; 5.4; Annex 2; Annex 8 (p. 19-21; 49; 59-60)
- Curtailment compensation
- Applicable Source: cl. 2.5; 5.7 (p. 14-15; 23)
- Summary of curtailment arrangements
- Grid constraints and NITS failures (trips beyond 100 hours a year), political FM and ECG failures are Excusable Events: capacity is deemed available and ECG keeps paying the Fixed O&M Charge. Dispatch below 60% is paid as deemed energy. Source: cl. 2.5; 'Excusable Event'; 5.7 (p. 7; 14-15; 23)
Force majeure, default and termination
- Force majeure provisions
- Political FM (war, change in law, terrorism, boycotts, nationalisation, failure to issue approvals) and Other FM. ECG cannot claim FM for payment obligations. Either party may terminate after 365 consecutive days of FM. ECG pays the Early Termination Fee (net of insurance) plus documented costs for political FM, FM affecting ECG, or where ECG elects to terminate for other FM affecting AKSA; no fee if AKSA terminates for other (non-political) FM affecting AKSA. Source: cl. 14.1; 14.2(b); 14.5 (p. 27-30)
- Termination rights
- AKSA may terminate for ECG Events of Default: uncured material breach (60 days), payment default (30 days after notice), insolvency, sanctions, revocation, nationalisation, change-in-law illegality (90 days), failure to implement a change-in-law tariff adjustment (60 days). ECG may terminate for AKSA default: material breach (15 days), misrepresentation, availability below 60% over 365 days, insolvency, abandonment. Either party may terminate if conditions precedent are unmet 15 months after signing (no liability). Source: cl. 22.1-22.4; 1.4(c)-(d); 14.5 (p. 34-36; 13; 29)
- Termination compensation: seller default
- No Compensation Source: cl. 5.6(c); 22.4 (p. 23; 36)
- Termination compensation: political force majeure
- Revenue-based: fixed-period charges Source: cl. 14.5(b) (p. 29-30)
- Summary of termination compensation framework
- Reciprocal Early Termination Fee = Capital Recovery Charge + Monthly Fixed O&M Charge that would be invoiced monthly with the plant at available/deemed capacity, for the lesser of 60 months or the remaining term. Paid by ECG in USD offshore within 90 days on ECG default and on FM termination (plus documented costs); paid by AKSA to ECG on AKSA default. Liability cap of US$25m excludes the fee; lost profit excluded otherwise; claims must be brought within 6 months. Plant stays AKSA's and is exported. Source: 'Early Termination Fee'; cl. 5.6(b)-(c); 14.5(b); 19.1-19.3; 22.5 (p. 5, 7; 23; 29-30; 32-33; 36)
Dispute resolution
- Governing law
- Laws of Ghana (arbitration clause governed by English law) Source: cl. 23.2; 26.1(b) (p. 37; 39)
- Dispute resolution: negotiation / mediation
- Yes Source: cl. 25.1 (p. 37)
- Dispute resolution: expert determination
- Yes Source: cl. 25.3-25.4 (p. 37-38)
- Dispute resolution: arbitration
- Yes Source: cl. 26 (p. 38-40)
- Dispute resolution: court proceedings
- No Source: cl. 26.4 (p. 39-40)
- Dispute resolution: other
- No
- Arbitration seat
- London, United Kingdom (alternative seat if award not readily enforceable in Ghana) Source: cl. 26.1(c) (p. 39)
- Applicable arbitration rules
- LCIA Rules; 3 arbitrators; English language Source: cl. 26.1(b), (d), (f) (p. 38-39)
Amendments
- Number of amendments executed
- Not in contract (base PPA only; no amendments in the set provided) Source: cl. 24.1 (p. 37)