GH-PPA-08
20 MW Thermal Generating Plant, Saltpond, Ghana
Lushann International Power Development (Ghana) Ltd · Thermal (Gas) · 20.00 MW · Near Saltpond, Central Region, Ghana
GH-PPA-08
20 MW Thermal Generating Plant, Saltpond, Ghana
Lushann International Power Development (Ghana) Ltd · Thermal (Gas) · 20.00 MW · Near Saltpond, Central Region, Ghana
Summary
A 20 MW natural gas plant near Saltpond (Phase I of a contemplated ~400 MW expansion, not committed under this PPA), supplying ECG under a 20-year capacity-and-energy PPA signed 20 May 2008. The tariff combines a 3.89 US cents/kWh energy charge with a 3.0 US cents/kWh capacity charge, both adjusted annually for fuel cost and inflation, with a take-or-pay obligation.
Key terms
- Offtaker
- Electricity Company of Ghana (ECG)
- Signing date
- 2008-05-20
- Financial close
- Not stated
- Commercial operation
- Within 2 years of the signing date (i.e. by approximately 20 May 2010), the date on which the Seller notifies the Buyer that the 20MW Facility has been commissioned and is available for commercial operation. Source: cl. 1.8 (p. 7)
- Contract end
- 2028-05-20
- Contract duration
- 20 years
- Contract status
- Active
- Project status
- Not recorded
- Tariff structure
- Capacity + Energy
- Capacity charge
- Two components, both at a Capacity Charge Rate (CCR) of US$0.030/kWh (3.0 US cents/kWh) as approved by PURC: Capacity Charge 1 = Net Energy x CCR, payable when the Facility is available and the Buyer accepts the energy; Capacity Charge 2 = [(Contracted Capacity x Available Hours x Available Days) - Net Energy] x CCR, payable when the Facility is available but the Buyer does not take the available energy (i.e. a deemed-energy charge); if Capacity Charge 2 is zero or negative, no capacity charge applies. Source: cl. 6.1.2-6.1.3 (p. 11-12)
- Energy charge
- USD 0.0389/kWh
- Key risk features
- Take-or-pay
- Indexation formula
- Energy Price adjusted annually via EP(new) = EP(old) + FPA + AIA, where FPA tracks actual fuel cost changes (natural gas or liquid fuel) from a US$4/MMBTU base and AIA is an annual inflation allowance approved by PURC. Both the Energy Price and the Capacity Charge are additionally renegotiated with PURC and the Buyer after the first 10 years of the 20-year term.
Project overview
- Installed capacity (MW)
- 20 MW (Phase I / first phase). The recitals contemplate a possible future expansion to approximately 400 MW in total, via a second phase of approximately 380 MW, subject to a separate commitment by the Buyer based on demand. Source: Recitals; cl. 11.2(e) (p. 6; 16)
- Commercial operation date (COD)
- Within 2 years of the signing date (i.e. by approximately 20 May 2010), the date on which the Seller notifies the Buyer that the 20MW Facility has been commissioned and is available for commercial operation. Source: cl. 1.8 (p. 7)
- Contract term (years)
- 20 Source: cl. 4 (p. 10)
Contracting parties
- Transmission service provider
- Not stated; no separate transmission service provider is named. Power is delivered directly to ECG's own Saltpond 33kV Primary Substation (the Point of Delivery, cl. 1.27), i.e. ECG (the Buyer) is itself the interconnecting grid/distribution owner at the delivery point. Source: cl. 1.27; 3.2 (p. 8; 9)
- Government support entity
- Not addressed in the PPA itself; may be addressed in related documents. Correspondence included ahead of the PPA in this file (an ECG letter of 15 July 2008 to the Minister of Energy, forwarded to the Minister of Finance on 18 July 2008) shows ECG requesting a Government Guarantee (Payment Security) from the Ministry of Finance so the Seller could access project financing. Source: Cover correspondence, pp.2-4 (p. 2-4)
- Project sponsors / shareholders
- Not in contract
- Ultimate beneficial owner(s)
- Not in contract
Commercial terms
- Contract type
- Capacity and Energy PPA Source: cl. 6.1 (p. 11)
- Contracted capacity (MW)
- 20 MW Source: cl. 1.5 (p. 7)
- Tariff currency
- US Dollars (payable in USD or the Ghana cedi equivalent at the prevailing exchange rate) Source: cl. 6.1.1; 9.1; 10 (p. 11; 14; 15)
- Capacity charge
- Two components, both at a Capacity Charge Rate (CCR) of US$0.030/kWh (3.0 US cents/kWh) as approved by PURC: Capacity Charge 1 = Net Energy x CCR, payable when the Facility is available and the Buyer accepts the energy; Capacity Charge 2 = [(Contracted Capacity x Available Hours x Available Days) - Net Energy] x CCR, payable when the Facility is available but the Buyer does not take the available energy (i.e. a deemed-energy charge); if Capacity Charge 2 is zero or negative, no capacity charge applies. Source: cl. 6.1.2-6.1.3 (p. 11-12)
- Energy charge
- Total Energy Charge = Net Energy at the Point of Delivery x Unit Energy Price of 3.89 US cents/kWh, as negotiated and approved by PURC (cl. 6.1.1). Together with the 3.0 US cents/kWh Capacity Charge 1 this makes up the 6.89 US cents/kWh billing rate for delivered energy in cl. 9.1 (see row 28). Source: cl. 6.1.1; 9.1 (p. 11; 14)
- Tariff escalation mechanism
- Energy Price adjusted using EP(new) = EP(old) + FPA + AIA, where FPA (fuel price adjustment) tracks actual changes in fuel cost (Natural Gas or liquid fuel) from a base cost of US$4/MMBTU of Natural Gas, and AIA is an annual inflation allowance approved by PURC, reviewed annually. Both the Energy Price and the Capacity Charge are additionally re-negotiated with PURC and the Buyer after the first 10 years of the 20-year term. Source: cl. 6.2; 9.1 (p. 12; 14)
- Indexation: inflation
- Yes Source: cl. 6.2 (p. 12)
- Indexation: foreign exchange
- No Source: cl. 10 (p. 15)
- Indexation: fuel price
- Yes Source: cl. 6.2 (p. 12)
- Indexation: none / fixed tariff
- No
- Indexation: other
- No
- Summary of indexation methodology
- Energy Price adjusted annually via EP(new) = EP(old) + FPA + AIA, where FPA tracks actual fuel cost changes (natural gas or liquid fuel) from the US$4/MMBTU base and AIA is an annual inflation allowance approved by PURC. Both the Energy Price and the Capacity Charge are additionally renegotiated with PURC and the Buyer after the first 10 years of the 20-year term (cl. 9.1). Source: cl. 6.2; 9.1 (p. 12; 14)
- Billing and payment cycle
- Monthly. Seller invoices within 4 days after month end (cl. 9.2); Buyer disputing an invoice has 10 working days to submit justification (paying the undisputed portion meanwhile), Seller has 10 working days to respond, and any Party may flag an invoice as disputed within 60 days of its date (cl. 9.3). Billing errors are corrected within 21 days, with over/under-payments refunded or invoiced within 14 days (cl. 9.4). Payment (energy, capacity charge and fuel cost adjustments) is due within 60 days of invoice dispatch, payable in US dollars or Ghana cedi equivalent at the then-prevailing average interbank USD exchange rate (cl. 10). Arrears bear interest at the Ghana inter-bank interest rate at the time of default (cl. 14, 'Payment Guarantees'). Source: cl. 9.2-9.4; 10; 14 (p. 14-15; 15; 18)
Government and consumer exposure
- Take-or-pay obligation
- Yes Source: cl. 6.1.3; 20.2 (p. 11-12; 20)
- Take-or-pay details
- Capacity Charge 2 = [(Contracted Capacity x Available Hours x Available Days) - Net Energy] x Capacity Charge Rate (US$0.030/kWh), payable whenever the Facility is available but the Buyer does not take the available energy, unless the result is zero or negative (cl. 6.1.3). Separately, clause 20.2 requires the Buyer to pay the Seller the capacity charge if it is unable to buy the stated quarterly reference quantity of energy (0.04 GWh, as printed - see row 11) for reasons not attributable to the Seller. Source: cl. 6.1.3; 20.2 (p. 11-12; 20)
- Government guarantee
- Not stated Source: cl. 14 (p. 18)
- Letter of support
- No
- Foreign exchange protection mechanism
- Yes Source: cl. 10 (p. 15)
- Foreign exchange protection details
- The total invoice may be paid in US dollars or the Ghana cedi equivalent, converted at the average interbank exchange rate for the US dollar at the time of payment (cl. 10). Because the cedi amount floats with the prevailing rate rather than being fixed at contract signing, this protects the Seller from cedi depreciation between invoicing and payment; no separate reconciliation or hedging mechanism is stated. Source: cl. 10 (p. 15)
- Other government commitments
- Environmental Protection Agency approvals and an Energy Commission Operational License/Approvals are conditions precedent to the Agreement becoming effective (cl. 5). PURC approves and periodically reviews the Energy Price, Capacity Charge Rate and annual inflation allowance (cl. 6.1.1, 6.1.2, 6.2, 9.1). Correspondence attached to this file shows ECG requesting a Government Guarantee (Payment Security) from the Ministry of Finance to support the Seller's project financing (see row 44), but this is outside the signed PPA text. No sovereign immunity waiver, nationalization-damages clause, or expropriation clause was found in the PPA. Source: cl. 5; 6.1.1-6.2; 9.1; cover correspondence (p. 10; 11-12; 14; 2-4)
- Fiscal incentives and non-tariff government support
- No tax holiday, duty/VAT exemption, stabilization clause, or concessional finance provision was found. 'Applicable taxes are extras' on both the Energy Charge and the Capacity Charge (cl. 9.1) - i.e. taxes are added on top of the stated rates and passed through to the Buyer via the invoice, which 'shall include all the taxes applicable to the Buyer' (cl. 9.2). The Seller is responsible for all aspects of delivering energy to the Point of Delivery at its own cost (cl. 3.2), so no land or interconnection cost is expressly allocated to government. Source: cl. 3.2; 9.1-9.2 (p. 9; 14)
Risk allocation
- Fuel supply risk borne by
- Shared Source: cl. 5(1); 6.2; 11.1(a) (p. 10; 12; 15)
- Resource availability risk borne by
- Not applicable
- Foreign exchange risk borne by
- Offtaker Source: cl. 10 (p. 15)
- Change in law risk borne by
- Not addressed
- Transmission and grid availability risk borne by
- Not addressed Source: cl. 3.2; 11.1(f) (p. 9; 16)
- Summary of key risk allocation provisions
- Fuel supply/availability risk: shared - Seller must secure a firm gas supply arrangement as a condition precedent and is generally responsible for fuel logistics, while fuel price changes pass through to the Buyer via the Energy Price adjustment formula (cl. 6.2). Resource availability risk: not applicable (thermal). FX risk: Offtaker - the tariff is USD-denominated and cedi payments are converted at the prevailing rate at the time of payment (cl. 10), so ECG bears the cost of sourcing USD value. Change in law: not addressed anywhere in the text. Transmission/grid risk: not clearly addressed - the Buyer (ECG) is itself the grid owner at the Point of Delivery, so there is no separate grid-availability allocation comparable to other Ghana PPAs. Overall, performance risk sits mainly with the Seller (90% availability target, default if delivery falls below 60% of Annual Energy over 90 days), while payment and offtake risk sit mainly with the Buyer (capacity charge payable on available-but-untaken energy). Source: cl. 3.2; 5(1); 6.2; 10; 11.1 (p. 9-12; 15-16)
Performance obligations
- Performance guarantee
- Yes Source: cl. 11.1(d); 19.1; 20.1-20.2 (p. 16; 19; 20)
- Curtailment compensation
- Applicable Source: cl. 6.1.3; 20.2 (p. 11-12; 20)
- Summary of curtailment arrangements
- When the Facility is available but the Buyer chooses not to take the available energy, the Seller is compensated via Capacity Charge 2 = [(Contracted Capacity x Available Hours x Available Days) - Net Energy] x Capacity Charge Rate (cl. 6.1.3), and separately, if the Buyer cannot buy the stated quarterly reference quantity of energy for reasons not attributable to the Seller, the Buyer must pay the Seller the capacity charge (cl. 20.2). By contrast, the Seller may interrupt supply for safety emergencies or agreed maintenance (cl. 12) with no compensation to the Buyer specified for those Seller-side interruptions, beyond the general default/Liquidated Damages regime that applies if delivery falls below 60% of the anticipated Annual Energy over 90 days (cl. 19.1, 20.1). During any extended interruption or restriction of the Seller's supply, the Buyer may, on notice, buy the shortfall from third parties (cl. 12). Source: cl. 6.1.3; 12; 19.1; 20.1-20.2 (p. 11-12; 17; 19; 20)
Force majeure, default and termination
- Force majeure provisions
- Force Majeure is defined broadly (war, revolution, riot, civil commotion, acts of God, explosion, fire, storm, earthquake, epidemic, quarantine, and strikes not limited to the Seller's own employees/subcontractor) (Section 13). A Party is excused from performance while a qualifying event continues, provided it proves the event meets the definition, was outside its control/not its fault, and it took reasonable precautions to avoid or mitigate the failure. Notice must be given as soon as possible, and the affected Party must resume performance with the least possible delay once the event ends. No payment relief or termination right is tied specifically to Force Majeure anywhere in the Agreement. Source: Section 13 (p. 17-18)
- Termination compensation: seller default
- Not stated Source: cl. 19.1; 20.1-20.2 (p. 19; 20)
- Termination compensation: buyer default
- Not stated Source: cl. 19.2; 20.3 (p. 19; 20-21)
- Termination compensation: political force majeure
- Not stated Source: Section 13 (p. 17-18)
Dispute resolution
- Governing law
- Laws of the Republic of Ghana Source: cl. 22 (p. 21)
- Dispute resolution: negotiation / mediation
- Yes Source: cl. 23.1 (p. 21)
- Dispute resolution: expert determination
- No
- Dispute resolution: arbitration
- Yes Source: cl. 23.1-23.2 (p. 21)
- Dispute resolution: court proceedings
- Yes Source: cl. 23.1 (p. 21)
- Dispute resolution: other
- No
- Arbitration seat
- Not stated in the PPA
- Applicable arbitration rules
- No institutional rules named (ad hoc arbitration). An Arbitration Committee of 3 arbitrators: each Party appoints one within 14 days of a dispute being declared for arbitration, and the two appointed arbitrators agree the third, failing which the Ghana Chamber of Commerce appoints the third. The Committee has 30 days to resolve the dispute by simple majority. Unlike most other reviewed PPAs, the decision is not stated to be final - a dissatisfied Party may go to court (cl. 23.1, see row 76). Source: cl. 23.2 (p. 21)
Amendments
- Number of amendments executed
- Not in contract (base PPA only; no amendments in the set provided) Source: cl. 25 (p. 21)